QUINTA VALORIZACION
PROYECTO
CORRESPONDIENTE AL MES DE : NOVIEMBRERESIDENTE DE OBRA : ING, RAUL CURASMA RAMOS FECHA DE PRESENTACION : 30/11/ 2013SUPERVISOR DE OBRA : ING. ALEX ANTONIO CARHUAMACA CANTO PERIODO : 01/07/2013 AL 31/07/2013DISTRITO : CHUPURO MONTO DEL PRESUPUESTO S/. 1,892,122.92PROVINCIA : HUANCAYO Avance Anterior 70.54%
DEPARTAMENTO : JUNIN Avance Actual 15.01% FECHA DE INICIO DE OBRA : 02/07/2013Avance Acumulado 85.55% PLAZO DE EJECUCION : 150 DiasSALDO 14.45% FECHA DE TERMINO PREVISTO : 02 DICIEMBRE DEL 2013
PARTIDA DESCRIPCIONPRESUPUESTO REFERENCIAL AVANCE
SALDO %
UND METRADOP.Unitario Presupuesto ANTERIOR ACTUAL ACUMULADO
S/. S/. METRADO VALORIZADO METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO
DESAGUE PLUVIAL01.00.00 TRABAJOS PRELIMINARES 1,219.98 1,219.98 0.00 1,219.98 0.00
01.01.00 TRAZO Y REPLANTEO ML 975.98 1.25 1,219.98 975.98 1,219.98 0.00 0.00% 975.98 1,219.98 100.00% 0.00 0.00 0.00%
02.00.00 MOVIMIENTO DE TIERRAS 46,612.23 45,892.80 661.60 46,612.21 0.00
02.01.00 EXCAVACIONES 46,612.23 45,892.80 661.60 46,612.21 0.00
02.01.01 EXCAVACION DE ZANJA CON MAQUINARIA DE TUBERIA PARA CONEXIÓN M3 838.00 11.00 9,218.00 838.00 9,218.00 0.00 0.00 0.00% 838.00 9,218.00 100.00% 0.00 0.00 0.00%
02.01.02 EXCAVACION ZANJA MANUAL SUMIDERO A MATRIZ DE DES.PLUVIAL DE TUB. ARA SUMIDERO A RED MATRIZ M3 137.98 25.58 3,529.53 137.98 3,529.53 0.00 0.00 0.00% 137.98 3,529.53 100.00% 0.00 0.00 0.00%
02.01.03 EXCAVACIONES PARA BUZONES M3 43.73 25.58 1,118.70 38.79 992.25 4.94 126.37 11.30% 43.73 1,118.61 100.00% 0.00 0.00 0.00%
02.01.04 EXCAVACION PARA SUMIDERO SUMIDERO TIPICO M3 41.92 25.58 1,072.25 39.66 1,014.50 2.26 0.00 0.00% 41.92 1,072.31 100.00% 0.00 0.00 0.00%
02.01.05 REFINE Y NIVELADO DE ZANJA P/TUBERIA DE TRAZO Y REPLANTEO ML 838.00 4.70 3,938.60 724.12 3,403.36 113.88 535.24 13.59% 838.00 3,938.60 100.00% 0.00 0.00 0.00%
02.01.06 PREPARACION CAMA DE APOYO ML 815.50 6.15 5,015.33 815.50 5,015.33 0.00 0.00 0.00% 815.50 5,015.33 100.00% 0.00 0.00 0.00%
02.01.07 RELLENO Y COMPACTADO DE ZANJA ML 815.50 27.86 22,719.83 815.50 22,719.83 0.00 0.00 0.00% 815.50 22,719.83 100.00% 0.00 0.00 0.00%
| OBRAS DE CONCRETO 30,355.71 20,305.25 7,251.04 27,556.82 2,798.04
03.01.00 BUZONES 30,355.71 20,305.25 7,251.04 27,556.82 2,798.04
03.01.01. ENCOFRADO Y DESENCOFRADO H=1,65 M2 93.06 16.17 1,504.78 73.08 1,181.64 19.98 323.08 21.47% 93.06 1,504.72 100.00% 0.00 0.00 0.00%
03.01.02 SOLADO DE CONCRETO fc=140kg/cm2 M3 3.98 212.73 847.20 2.66 565.86 1.32 280.80 33.15% 3.98 847.20 100.00% 0.00 0.00 0.00%
03.01.03 CONCRETO Fc=175 kg/cm2 en BUZON M3 17.52 262.31 4,596.46 15.27 4,005.47 2.25 590.20 12.84% 17.52 4,595.67 100.00% 0.00 0.00 0.00%
03.01.04 CONCRETO Fc=2175 kg/cm2 en teho h=0,20m M3 5.31 265.16 1,408.00 4.34 1,150.79 0.97 257.21 18.27% 5.31 1,408.00 100.00% 0.00 0.00 0.00%
03.01.05 ACERO DE REFUERZO Fy=4200 en buzones ML 30.00 5.55 166.50 24.10 133.76 5.90 32.75 19.67% 30.00 166.50 100.00% 0.00 0.00 0.00%
03.01.06 TARRAJEO INTERIOR BUZON M2 106.20 7.98 847.48 84.78 676.54 21.42 170.93 20.17% 106.20 847.48 100.00% 0.00 0.00 0.00%
03.01.07 MARCO Y TAPA DE FºFº EN BUZON UND 15.00 1,399.02 20,985.30 9.00 12,591.18 4.00 5,596.08 26.67% 13.00 18,187.26 86.67% 2.00 2,798.04 13.33%
04.00.00 SUMIDEROS 8,278.75 5,410.91 0.00 5,410.91 2,867.83
04.01.00 SUMIDEROS 8,278.75 5,410.91 0.00 5,410.91 2,867.83
04.01.01 ENCOFRADOY DESENCOFRADO DE SUMIDEROS M2 109.35 24.54 2,683.45 69.76 1,711.91 0.00 0.00 0.00% 69.76 1,711.91 63.80% 39.59 971.54 36.20%
04.01.02 CONCRETO Fc=175 kg/cm2 en sumideros M3 17.81 248.24 4,420.29 11.37 2,822.49 0.00 0.00 0.00% 11.37 2,822.49 63.85% 6.44 1,597.80 36.15%
04.01.03 ACERO REFUERZOfy=4200 EN SUMIDEROS EN MUROS KG 54.00 5.60 302.40 32.46 181.78 0.00 0.00 0.00% 32.46 181.78 60.11% 21.54 120.62 39.89%
04.01.04 TARRAJEO INTERIOR DE SUMIDERO M2 109.35 7.98 872.61 87.06 694.74 0.00 0.00 0.00% 87.06 694.74 79.62% 22.29 177.87 20.38%
05.00.00 SUMINISTRO E INSTALACIONES 59,794.41 58,533.06 564.52 59,097.58 696.83
05.01.00 RED DE TUBERIAS 57,957.06 57,392.54 564.52 57,957.06 0.00
05.01.01 TUBERIA MATRIZ PVC DE 8" ML 328.00 56.85 18,646.80 328.00 18,646.80 0.00 0.00 0.00% 328.00 18,646.80 100.00% 0.00 0.00 0.00%
05.01.02 TUBERIA MATRIZ PVC DE 10" ML 510.00 56.85 28,993.50 500.07 28,428.98 9.93 564.52 1.95% 510.00 28,993.50 100.00% 0.00 0.00 0.00%
05.01.03 TUBERIA CONEXIÓN SUMIDERO A MATRIZ UPVC 6" ML 137.98 74.77 10,316.76 137.98 10,316.76 0.00 0.00 0.00% 137.98 10,316.76 100.00% 0.00 0.00 0.00%
05.02.00 INSTALACIONES METALICAS 1,837.35 1,140.52 0.00 1,140.52 696.83
05.02.01 VENTANA PARA SUMIDERO (0,70x0,25m) fierrosф 1/2 "ventana 70x30 UND 27.00 68.05 1,837.35 16.76 1,140.52 0.00 0.00 0.00% 16.76 1,140.52 62.07% 10.24 696.83 37.93%
06.00.00 VARIOS 6,892.28 0.00 0.00 0.00 6,892.28
06.01.00 TAJEA EN PROG 0+520 4,051.28 0.00 0.00 0.00 4,051.28
06.01.01 TUBERIA UPVC 10" PROG 0+520 ML 15.00 248.24 3,723.60 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,723.60 100.00%
06.01.02 CONCRETO Fc=175 kg/cm2 en caja rompe presion M3 1.22 248.24 302.85 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.22 302.85 100.00%
06.01.03 CONCRETO Fc=175 kg/cm2 en tapa de caja M3 0.10 248.24 24.82 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.10 24.82 100.00%
"MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"

06.02.00 TAJEA CONCRETO PROG 0+930 2,841.01 0.00 0.00 0.00 2,841.01
06.02.01 EXCAVACIONES MANUALES M3 5.40 25.58 138.13 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 5.40 138.13 100.00%
06.02.02 ENCOFRADO Y DESENCOFRADO M2 36.00 24.54 883.44 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 883.44 100.00%
06.02.03 SOLADO CONCRETO fc=140KG/CM2 M3 0.90 220.00 198.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.90 198.00 100.00%
06.02.04 CONCRETO Fc=175 kg/cm2 en ponton m3 2.70 248.24 670.25 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.70 670.25 100.00%
06.02.05 ACERO FY=4200 KG/CM2 KG 169.86 5.60 951.19 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 169.86 951.19 100.00%
PAVIMENTO RIGIDO07.00.00 OBRAS PROVISIONALES 3,231.42 2,631.42 300.00 2,931.42 300.00
07.01.00 ALMACEN Y CASETA DE GUARDIANIA dia 150.00 10.00 1,500.00 90.00 900.00 30.00 300.00 20.00% 120.00 1,200.00 80.00% 30.00 300.00 20.00%
07.02.00 MOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.00 480.00 480.00 1.00 480.00 0.00 0.00 0.00% 1.00 480.00 100.00% 0.00 0.00 0.00%
07.03.00 CARTE DE IDENTIFICACION DE OBRA und 1.00 1,251.42 1,251.42 1.00 1,251.42 0.00 0.00 0.00% 1.00 1,251.42 100.00% 0.00 0.00 0.00%
08.00.00 TRABAJOS PRELIMNARES 17,131.39 17,131.39 0.00 17,131.39 0.00
08.01.00 TRAZO DE NIVELES Y REPLANTEO (GENERAL) m2 7,344.00 1.06 7,784.64 7344.00 7,784.64 0.00 0.00 0.00% 7,344.00 7,784.64 100.00% 0.00 0.00 0.00%
08.02.00 DEMOLICION DE PAVIMENTO EXISTENTE m2 518.40 18.03 9,346.75 518.40 9,346.75 0.00 0.00 0.00% 518.40 9,346.75 100.00% 0.00 0.00 0.00%
09.00.00 MOVIMIENTO DE TIERRAS 10,516.20 10,115.76 156.95 10,272.71 242.76
09.01.00 CORTE DE TERRENO A NIVEL DE SUB RASANTE m3 2,570.40 3.69 9,484.78 2570.20 9,484.04 0.00 0.00 0.00% 2,570.20 9,484.04 100.00% 0.00 0.00 0.00%
09.02.00 EXCAVACION MANUAL PARA BADEN M3 23.72 9.37 222.26 6.97 65.31 16.75 156.95 70.62% 23.72 222.26 100.00% 0.00 0.00 0.00%
09.03.00 EXCAVACION MANUAL PARA SARDINEL M3 86.36 9.37 809.17 60.45 566.42 0.00 0.00 0.00% 60.45 566.42 70.00% 25.91 242.76 30.00%
10.00.00 ELIMINACION DE MATERIAL EXEDENTE 82,344.27 65,360.33 16,983.86 82,344.19 0.08
10.01.00 ACARREO INTERNO DE MATERIAL m3 3,216.57 15.30 49,213.57 2382.19 36,447.51 834.38 12,766.01 25.94% 3,216.57 49,213.52 100.00% 0.00 0.05 0.00%
10.02.00 TRANSPORTE DE CARGIO(ELIMINACION) M3 3,216.57 10.30 33,130.70 2807.07 28,912.82 409.50 4,217.85 12.73% 3,216.57 33,130.67 100.00% 0.00 0.03 0.00%
11.00.00 PAVIMENTO RIGIDO 1,010,508.93 722,701.46 180,280.51 902,981.97 107,526.95
11.01.00 MEJORAMIENTO DE LA SUB RASANTE 248,404.79 185,211.45 63,193.35 248,404.79 0.00
11.01.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB RASANTE M3 1,321.92 79.30 104,828.26 973.52 77,200.14 348.40 27,628.12 26.36% 1,321.92 104,828.26 100.00% 0.00 0.00 0.00%
11.01.02 SELECCIÓN DE MATERIAL P7MEJ.SUB RASANTE(ZARANDEADO) M3 1,101.60 51.01 56,192.62 786.89 40,139.26 314.71 16,053.36 28.57% 1,101.60 56,192.62 100.00% 0.00 0.00 0.00%
11.01.03 CARGUIO P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 27.55 30,349.08 830.48 22,879.72 271.12 7,469.36 24.61% 1,101.60 30,349.08 100.00% 0.00 0.00 0.00%
11.01.04 TRANSORTE P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 15.30 16,854.48 694.49 10,625.70 407.11 6,228.78 36.96% 1,101.60 16,854.48 100.00% 0.00 0.00 0.00%
11.01.05 EXTR. RIEGO Y COMPACTACION MEJORAM. SUB RASANTE e= 0.15 MTS. M2 7,581.20 5.30 40,180.36 6484.27 34,366.63 1096.93 5,813.73 14.47% 7,581.20 40,180.36 100.00% 0.00 0.00 0.00%
11.02.00 SUB BASE GRANULAR 762,104.13 537,490.01 117,087.17 654,577.18 107,526.95
11.02.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB BASE M3 1,812.21 79.30 143,708.25 1201.50 95,278.95 610.71 48,429.30 33.70% 1,812.21 143,708.25 100.00% 0.00 0.00 0.00% 3492
11.02.02 SELECCIÓN DE MATERIAL P7MEJ.SUB BASE(ZARANDEADO) M3 1,812.21 51.01 92,440.83 1342.73 68,492.66 234.74 11,974.09 12.95% 1,577.47 80,466.74 87.05% 234.74 11,974.09 12.95% 3081.176471
11.02.03 CARGUIO P/MEJ. DE SUB BASE DE LA SELLECCION DEL MATERIAL M3 1,812.21 27.55 49,926.39 1060.50 29,216.78 234.74 6,467.09 12.95% 1,295.24 35,683.86 71.47% 516.97 14,242.52 28.53%
11.02.04 EXTENDIDO Y RIEGO COMPACTADO M2 7,344.00 5.30 38,923.20 4517.41 23,942.27 1413.95 7,493.94 19.25% 5,931.36 31,436.21 80.76% 1,412.64 7,486.99 19.24%
11.02.05 ENCOFRADO Y DESENCOFRADO DE LOSA M2 1,224.00 28.78 35,226.72 884.53 25,456.77 251.24 7,230.69 20.53% 1,135.77 32,687.46 92.79% 88.23 2,539.26 7.21% 1387.2
11.02.06 CONCRETO fc=210 kg/cm2 M3 1368.49 281.26 384,901.50 1004.75 282,595.99 114.21 32,122.70 8.35% 1,118.96 314,718.69 81.77% 249.53 70,182.81 18.23% 1224
11.02.07 ACERO fy=4200kg/cm2 kg 3,081.17 5.51 16,977.25 2269.80 12,506.60 611.50 3,369.37 19.85% 2,881.30 15,875.96 93.51% 199.87 1,101.28 6.49% 1550.96
12.00.00 BADEN INTERSECCION DE VIAS Y SARDINELES 128,163.31 100,964.40 16,287.70 117,252.10 10,911.22 1368.494118
12.01.00 BADEN INTERSECCION DE VIAS 6,785.82 1,993.98 1,993.98 3,987.96 2,797.86
12.01.01 ENCOFRADO Y DESENCOFRADO DE BADEN M2 23.72 21.24 503.81 6.97 148.04 6.97 148.04 29.38% 13.94 296.09 58.77% 9.78 207.73 41.23%
12.01.02 CONCRETO fc=210 kg/cm2 en BADEN M3 23.72 264.84 6,282.00 6.97 1,845.93 6.97 1,845.93 29.38% 13.94 3,691.87 58.77% 9.78 2,590.14 41.23%
12.02.00 SARDINEL EXPUESTO 121,377.50 98,970.42 14,293.72 113,264.14 8,113.36
12.02.01 ENCOFRADO DESENCOFRADO SARDINEL EXPUESTO M2 1,736.47 51.02 88,594.70 1421.87 72,543.81 180.00 9,183.60 10.37% 1,601.87 81,727.41 92.25% 134.60 6,867.29 7.75% 1968
12.02.02 CONCRETO fc=175kg/cm2 en sardinel M3 130.23 251.73 32,782.80 104.98 26,426.62 20.30 5,110.12 15.59% 125.28 31,536.73 96.20% 4.95 1,246.06 3.80%
13.00.00 OBRAS DE CONCRETO ARMADO 64,304.05 0.00 0.00 0.00 64,304.05
13.01.00 MURO DE CONTENCION 64,304.05 0.00 0.00 0.00 64,304.05 147.6
13.01.01 EXCAVACION MANUAL M3 318.00 26.39 8,392.02 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 318.00 8,392.02 100.00%
13.01.02 RELLENO CON MATERIAL SELECCIONADO M3 156.00 36.05 5,623.80 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 156.00 5,623.80 100.00%
13.01.03 CONCRETO fc=210 kg/cm2 en Muros M3 81.60 265.69 21,680.30 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 81.60 21,680.30 100.00%
13.01.04 ENCOFRADO Y DESENCOFRADO EN MUROS M2 561.00 28.41 15,938.01 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 561.00 15,938.01 100.00%
13.01.05 ACERO DE REFUEZO FY=4200 kg/cm2 kg 2,450.66 5.17 12,669.91 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2,450.66 12,669.91 100.00%
14.00.00 JUNTAS DE DILATACION 7,726.11 2,189.07 1,947.40 4,136.47 3,589.64
14.01.00 JUNTAS ASFALTICAS 7,726.11 2,189.07 1,947.40 4,136.47 3,589.64
14.01.01 RELLENO DE JUNTAS CON ASFALTO ML 2,971.58 2.60 7,726.11 841.95 2,189.07 749.00 1,947.40 25.21% 1,590.95 4,136.47 53.54% 1,380.63 3,589.64 46.46% 3367.8
15.00.00 SEÑALIZACION 17,609.90 3,016.00 0.00 3,016.00 14,593.90
15.01.00 SEÑALIZACION HORIZONTAL 17,609.90 3,016.00 0.00 3,016.00 14,593.90

15.01.01 PINTURA LINEAL EN SARDINEL ML 1,658.00 4.46 7,394.68 400.00 1,784.00 0.00 0.00 0.00% 400.00 1,784.00 24.13% 1,258.00 5,610.68 75.87%
15.01.02 PINTURA LINELA DISCONTINUA EJE VIA ML 882.35 6.16 5,435.28 200.00 1,232.00 0.00 0.00 0.00% 200.00 1,232.00 22.67% 682.35 4,203.28 77.33% 1879.26
15.01.03 PINTURA ZONAL (CRUCE PEATONAL) M2 17.64 10.11 178.34 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 17.64 178.34 100.00%
15.01.04 SEÑALIZACION REGLAMENTARIAS UND 32.00 18.80 601.60 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 601.60 100.00%
15.01.05 SEÑALES DE TRANSITO UND 20.00 200.00 4,000.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,000.00 100.00% 1000
16.00.00 VARIOS 1,166.40 219.60 259.20 478.80 687.60
16.01.00 LIMPIEZA FINAL DE OBRA M2 6,480.00 0.18 1,166.40 1220.00 219.60 1440.00 259.20 22.22% 2,660.00 478.80 41.05% 3,820.00 687.60 58.95%
17.00.00 PLACA RECORDATORIA 802.12 0.00 0.00 0.00 802.12 20
17.01.00 PLACA RECORDATORIA UND 1.00 802.12 802.12 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 802.12 100.00%
1,496,657.47 1,055,691.43 224,692.78 1,280,442.56 216,213.30
GASTOS GENERALES 15% 224,498.62 158,353.71 33,703.92 192,066.38 32,432.00
SUB TOTAL 1,721,156.09 1,214,045.14 258,396.70 1,472,508.94 248,645.30
EXPEDIENTE TECNICO 22,000.00 15,518.05 3,302.85 18,820.91 3,178.21
SUPERVISION 60,000.00 42,321.97 9,007.78 51,329.75 8,667.85
COSTO DE LA OBRA 1,803,156.09 70.54% 1,271,885.16 15.01% 270,707.34 85.55% 1,542,659.60 14.45% 260,491.35
900.00 7.20
6,480.00
COSTO DIRECTO TOTAL

1020
900
1020
900
1020
900
1020
900
1736.470588
1020
900
130.2352941
1020
900
2971.588235

1020
900
1658.170588
1020
900
882.3529412
1020
90017.64705882

SEGUNDA VALORIZACION
PROYECTO
CORRESPONDIENTE AL MES DE : AGOSTO - 2013RESIDENTE DE OBRA : FECHA DE PRESENTACION : 01/08/2013SUPERVISOR DE OBRA : PERIODO : 01/08/2013 AL 31/08/2013DISTRITO : CHUPURO MONTO DEL PRESUPUESTO S/. 1,892,122.92PROVINCIA : HUANCAYO Avance Anterior 8.43%
DEPARTAMENTO : JUNIN Avance Actual 12.76% FECHA DE INICIO DE OBRA : 02/07/2013Avance Acumulado 21.20% PLAZO DE EJECUCION : 150 DiasSALDO 78.80% FECHA DE TERMINO PREVISTO : 02 DICIEMBRE DEL 2013
PARTIDA DESCRIPCIONPRESUPUESTO REFERENCIAL AVANCE
SALDO %
UND METRADOP.Unitario Presupuesto ANTERIOR ACTUAL ACUMULADO
S/. S/. METRADO VALORIZADO METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO
DESAGUE PLUVIAL01.00.00 TRABAJOS PRELIMINARES 1,219.98 1,219.98 0.00 1,219.98 0.00
01.01.00 TRAZO Y REPLANTEO ML 975.98 1.25 1,219.98 975.98 1,219.98 0.00 0.00 0.00% 975.98 1,219.98 100.00% 0.00 0.00 0.00%
02.00.00 MOVIMIENTO DE TIERRAS 46,612.23 23,751.31 17,534.95 41,286.26 5,326.03
02.01.00 EXCAVACIONES 46,612.23 23,751.31 17,534.95 41,286.26 5,326.03
02.01.01 EXCAVACION DE ZANJA CON MAQUINARIA DE TUBERIA PARA CONEXIÓN M3 838.00 11.00 9,218.00 570.09 6,270.99 186.80 2,054.80 22.29% 756.89 8,325.79 90.32% 81.11 892.21 9.68%
02.01.02 EXCAVACION ZANJA MANUAL SUMIDERO A MATRIZ DE DES.PLUVIAL DE TUB. ARA SUMIDERO A RED M3 137.98 25.58 3,529.53 87.23 2,231.34 50.75 1,298.19 36.78% 137.98 3,529.53 100.00% 0.00 0.00 0.00%
02.01.03 EXCAVACIONES PARA BUZONES M3 43.73 25.58 1,118.70 12.34 315.66 12.34 315.66 28.22% 24.68 631.31 56.43% 19.05 487.38 43.57%
02.01.04 EXCAVACION PARA SUMIDERO SUMIDERO TIPICO M3 41.92 25.58 1,072.25 26.45 676.59 15.47 395.72 36.91% 41.92 1,072.31 100.01% 0.00 0.00 0.00%
02.01.05 REFINE Y NIVELADO DE ZANJA P/TUBERIA DE TRAZO Y REPLANTEO ML 838.00 4.70 3,938.60 534.12 2,510.36 190.00 893.00 22.67% 724.12 3,403.36 86.41% 113.88 535.24 13.59%
02.01.06 PREPARACION CAMA DE APOYO ML 815.50 6.15 5,015.33 347.19 2,135.22 291.27 1,791.31 35.72% 638.46 3,926.53 78.29% 177.04 1,088.80 21.71%
02.01.07 RELLENO Y COMPACTADO DE ZANJA ML 815.50 27.86 22,719.83 344.98 9,611.14 387.16 10,786.28 47.48% 732.14 20,397.42 89.78% 83.36 2,322.41 10.22%
| OBRAS DE CONCRETO 30,355.71 939.23 2,855.88 3,795.11 26,560.60
03.01.00 BUZONES 30,355.71 939.23 2,855.88 3,795.11 26,560.60
03.01.01. ENCOFRADO Y DESENCOFRADO H=1,65 M2 93.06 16.17 1,504.78 9.31 150.54 21.54 348.30 23.15% 30.85 498.84 33.15% 62.21 1,005.94 66.85%
03.01.02 SOLADO DE CONCRETO fc=140kg/cm2 M3 3.98 212.73 847.20 0.40 85.09 0.79 168.06 19.84% 1.19 253.15 29.88% 2.79 594.05 70.12%
03.01.03 CONCRETO Fc=175 kg/cm2 en BUZON M3 17.52 262.31 4,596.46 1.76 461.67 6.72 1,762.72 38.35% 8.48 2,224.39 48.39% 9.04 2,372.07 51.61%
03.01.04 CONCRETO Fc=2175 kg/cm2 en teho h=0,20m M3 5.31 265.16 1,408.00 0.53 140.53 1.48 392.44 27.87% 2.01 532.97 37.85% 3.30 875.03 62.15%
03.01.05 ACERO DE REFUERZO Fy=4200 en buzones ML 30.00 5.55 166.50 3.00 16.65 6.00 33.30 20.00% 9.00 49.95 30.00% 21.00 116.55 70.00%
03.01.06 TARRAJEO INTERIOR BUZON M2 106.20 7.98 847.48 10.62 84.75 18.93 151.06 17.82% 29.55 235.81 27.82% 76.65 611.67 72.18%
03.01.07 MARCO Y TAPA DE FºFº EN BUZON UND 15.00 1,399.02 20,985.30 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 20,985.30 100.00%
04.00.00 SUMIDEROS 8,278.75 0.00 1,987.90 1,987.90 6,290.85
04.01.00 SUMIDEROS 8,278.75 0.00 1,987.90 1,987.90 6,290.85
04.01.01 ENCOFRADOY DESENCOFRADO DE SUMIDEROS M2 109.35 24.54 2,683.45 0.00 0.00 24.30 596.32 22.22% 24.30 596.32 22.22% 85.05 2,087.13 77.78%
04.01.02 CONCRETO Fc=175 kg/cm2 en sumideros M3 17.81 248.24 4,420.29 0.00 0.00 4.20 1,042.61 23.59% 4.20 1,042.61 23.59% 13.61 3,377.68 76.41%
04.01.03 ACERO REFUERZOfy=4200 EN SUMIDEROS EN MUROS KG 54.00 5.60 302.40 0.00 0.00 11.23 62.89 20.80% 11.23 62.89 20.80% 42.77 239.51 79.20%
04.01.04 TARRAJEO INTERIOR DE SUMIDERO M2 109.35 7.98 872.61 0.00 0.00 35.85 286.08 32.78% 35.85 286.08 32.78% 73.50 586.53 67.22%
05.00.00 SUMINISTRO E INSTALACIONES 59,794.41 37,243.41 14,013.99 51,257.41 8,537.01
05.01.00 RED DE TUBERIAS 57,957.06 37,243.41 13,605.69 50,849.11 7,107.96
05.01.01 TUBERIA MATRIZ PVC DE 8" ML 328.00 56.85 18,646.80 156.00 8,868.60 109.39 6,218.82 33.35% 265.39 15,087.42 80.91% 62.61 3,559.38 19.09%
05.01.02 TUBERIA MATRIZ PVC DE 10" ML 510.00 56.85 28,993.50 436.00 24,786.60 44.00 2,501.40 8.63% 480.00 27,288.00 94.12% 30.00 1,705.50 5.88%05.01.03 TUBERIA CONEXIÓN SUMIDERO A MATRIZ UPVC 6" ML 137.98 74.77 10,316.76 47.99 3,588.21 65.34 4,885.47 47.35% 113.33 8,473.68 82.14% 24.65 1,843.08 17.86%
05.02.00 INSTALACIONES METALICAS 1,837.35 0.00 408.30 408.30 1,429.0505.02.01 VENTANA PARA SUMIDERO (0,70x0,25m) fierrosф 1/2 "ventana 70x30 UND 27.00 68.05 1,837.35 0.00 0.00 6.00 408.30 22.22% 6.00 408.30 22.22% 21.00 1,429.05 77.78%
"MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"

06.00.00 VARIOS 6,892.28 0.00 0.00 0.00 6,892.28
06.01.00 TAJEA EN PROG 0+520 4,051.28 0.00 0.00 0.00 4,051.28
06.01.01 TUBERIA UPVC 10" PROG 0+520 ML 15.00 248.24 3,723.60 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 15.00 3,723.60 100.00%
06.01.02 CONCRETO Fc=175 kg/cm2 en caja rompe presion M3 1.22 248.24 302.85 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.22 302.85 100.00%
06.01.03 CONCRETO Fc=175 kg/cm2 en tapa de caja M3 0.10 248.24 24.82 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.10 24.82 100.00%
06.02.00 TAJEA CONCRETO PROG 0+930 2,841.01 0.00 0.00 0.00 2,841.01
06.02.01 EXCAVACIONES MANUALES M3 5.40 25.58 138.13 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 5.40 138.13 100.00%
06.02.02 ENCOFRADO Y DESENCOFRADO M2 36.00 24.54 883.44 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 883.44 100.00%
06.02.03 SOLADO CONCRETO fc=140KG/CM2 M3 0.90 220.00 198.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.90 198.00 100.00%
06.02.04 CONCRETO Fc=175 kg/cm2 en ponton m3 2.70 248.24 670.25 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.70 670.25 100.00%
06.02.05 ACERO FY=4200 KG/CM2 KG 169.86 5.60 951.19 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 169.86 951.19 100.00%
PAVIMENTO RIGIDO07.00.00 OBRAS PROVISIONALES 3,231.42 1,623.42 386.40 2,009.82 1,221.60
07.01.00 ALMACEN Y CASETA DE GUARDIANIA dia 150.00 10.00 1,500.00 30.00 300.00 30.00 300.00 20.00% 60.00 600.00 40.00% 90.00 900.00 60.00%
07.02.00 MOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.00 480.00 480.00 0.15 72.00 0.18 86.40 18.00% 0.33 158.40 33.00% 0.67 321.60 67.00%
07.03.00 CARTE DE IDENTIFICACION DE OBRA und 1.00 1,251.42 1,251.42 1.00 1,251.42 0.00 0.00 0.00% 1.00 1,251.42 100.00% 0.00 0.00 0.00%
08.00.00 TRABAJOS PRELIMNARES 17,131.39 9,227.94 7,903.45 17,131.39 0.00
08.01.00 TRAZO DE NIVELES Y REPLANTEO (GENERAL) m2 7,344.00 1.06 7,784.64 7,344.00 7,784.64 0.00 0.00 0.00% 7,344.00 7,784.64 100.00% 0.00 0.00 0.00%
08.02.00 DEMOLICION DE PAVIMENTO EXISTENTE m2 518.40 18.03 9,346.75 80.05 1,443.30 438.35 7,903.45 84.56% 518.40 9,346.75 100.00% 0.00 0.00 0.00%
09.00.00 MOVIMIENTO DE TIERRAS 10,516.20 8,156.38 1,582.42 9,738.80 777.41
09.01.00 CORTE DE TERRENO A NIVEL DE SUB RASANTE m3 2,570.40 3.69 9,484.78 2,210.40 8,156.38 275.34 1,016.00 10.71% 2,485.74 9,172.38 96.71% 84.66 312.40 3.29%
09.02.00 EXCAVACION MANUAL PARA BADEN M3 23.72 9.37 222.26 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 23.72 222.26 100.00%
09.03.00 EXCAVACION MANUAL PARA SARDINEL M3 86.36 9.37 809.17 0.00 0.00 60.45 566.42 70.00% 60.45 566.42 70.00% 25.91 242.76 30.00%
10.00.00 ELIMINACION DE MATERIAL EXEDENTE 82,344.27 19,800.27 18,110.96 37,911.23 44,433.05
10.01.00 ACARREO INTERNO DE MATERIAL m3 3,216.57 15.30 49,213.57 188.40 2,882.52 714.79 10,936.29 22.22% 903.19 13,818.81 28.08% 2,313.38 35,394.76 71.92%
10.02.00 TRANSPORTE DE CARGIO(ELIMINACION) M3 3,216.57 10.30 33,130.70 1,642.50 16,917.75 696.57 7,174.67 21.66% 2,339.07 24,092.42 72.72% 877.50 9,038.28 27.28%
11.00.00 PAVIMENTO RIGIDO 1,068,791.01 3,816.00 57,396.91 61,212.91 1,007,578.10
11.01.00 MEJORAMIENTO DE LA SUB RASANTE 248,404.79 3,816.00 24,849.50 28,665.50 219,739.29
11.01.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB RASANTE M3 1,321.92 79.30 104,828.26 0.00 0.00 132.19 10,482.67 10.00% 132.19 10,482.67 10.00% 1,189.73 94,345.59 90.00%
11.01.02 SELECCIÓN DE MATERIAL P7MEJ.SUB RASANTE(ZARANDEADO) M3 1,101.60 51.01 56,192.62 0.00 0.00 110.34 5,628.44 10.02% 110.34 5,628.44 10.02% 991.26 50,564.17 89.98%
11.01.03 CARGUIO P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 27.55 30,349.08 0.00 0.00 110.16 3,034.91 10.00% 110.16 3,034.91 10.00% 991.44 27,314.17 90.00%
11.01.04 TRANSORTE P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 15.30 16,854.48 0.00 0.00 110.16 1,685.45 10.00% 110.16 1,685.45 10.00% 991.44 15,169.03 90.00%
11.01.05 EXTR. RIEGO Y COMPACTACION MEJORAM. SUB RASANTE e= 0.15 MTS. M2 7,581.20 5.30 40,180.36 720.00 3,816.00 758.12 4,018.04 10.00% 1,478.12 7,834.04 19.50% 6,103.08 32,346.32 80.50%
11.02.00 SUB BASE GRANULAR 820,386.22 0.00 32,547.41 32,547.41 787,838.81
11.02.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB BASE M3 1,812.21 79.30 143,708.25 0.00 0.00 181.22 14,370.75 10.00% 181.22 14,370.75 10.00% 1,630.99 129,337.51 90.00%
11.02.02 SELECCIÓN DE MATERIAL P7MEJ.SUB BASE(ZARANDEADO) M3 1,812.21 51.01 92,440.83 0.00 0.00 181.22 9,244.03 10.00% 181.22 9,244.03 10.00% 1,630.99 83,196.80 90.00%
11.02.03 CARGUIO P/MEJ. DE SUB BASE DE LA SELLECCION DEL MATERIAL M3 1,812.21 27.55 49,926.39 0.00 0.00 181.22 4,992.61 10.00% 181.22 4,992.61 10.00% 1,630.99 44,933.77 90.00%
11.02.04 EXTENDIDO Y RIEGO COMPACTADO M2 7,344.00 5.30 38,923.20 0.00 0.00 743.40 3,940.02 10.12% 743.40 3,940.02 10.12% 6,600.60 34,983.18 89.88%
11.02.05 ENCOFRADO Y DESENCOFRADO DE LOSA M2 1,387.20 28.78 39,923.62 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,387.20 39,923.62 100.00%
11.02.06 CONCRETO fc=210 kg/cm2 M3 1,550.96 281.26 436,223.01 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,550.96 436,223.01 100.00%
11.02.07 ACERO fy=4200kg/cm2 kg 3,492.00 5.51 19,240.92 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3,492.00 19,240.92 100.00%
12.00.00 BADEN INTERSECCION DE VIAS Y SARDINELES 144,348.53 20,846.88 78,123.54 98,970.42 45,378.10
12.01.00 BADEN INTERSECCION DE VIAS 6,785.82 0.00 0.00 0.00 6,785.82
12.01.01 ENCOFRADO Y DESENCOFRADO DE BADEN M2 23.72 21.24 503.81 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 23.72 503.81 100.00%
12.01.02 CONCRETO fc=210 kg/cm2 en BADEN M3 23.72 264.84 6,282.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 23.72 6,282.00 100.00%
12.02.00 SARDINEL EXPUESTO 137,562.71 20,846.88 78,123.54 98,970.42 38,592.29
12.02.01 ENCOFRADO DESENCOFRADO SARDINEL EXPUESTO M2 1,968.00 51.02 100,407.36 305.68 15,595.79 1116.19 56,948.01 56.72% 1,421.87 72,543.81 72.25% 546.13 27,863.55 27.75%
12.02.02 CONCRETO fc=175kg/cm2 en sardinel M3 147.60 251.73 37,155.35 20.86 5,251.09 84.12 21,175.53 56.99% 104.98 26,426.62 71.12% 42.62 10,728.73 28.88%
13.00.00 OBRAS DE CONCRETO ARMADO 64,304.05 6,133.56 971.15 7,104.72 57,199.33
13.01.00 MURO DE CONTENCION 64,304.05 6,133.56 971.15 7,104.72 57,199.33

13.01.01 EXCAVACION MANUAL M3 318.00 26.39 8,392.02 232.42 6,133.56 36.80 971.15 11.57% 269.22 7,104.72 84.66% 48.78 1,287.30 15.34%
13.01.02 RELLENO CON MATERIAL SELECCIONADO M3 156.00 36.05 5,623.80 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 156.00 5,623.80 100.00%
13.01.03 CONCRETO fc=210 kg/cm2 en Muros M3 81.60 265.69 21,680.30 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 81.60 21,680.30 100.00%
13.01.04 ENCOFRADO Y DESENCOFRADO EN MUROS M2 561.00 28.41 15,938.01 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 561.00 15,938.01 100.00%
13.01.05 ACERO DE REFUEZO FY=4200 kg/cm2 kg 2,450.66 5.17 12,669.91 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2,450.66 12,669.91 100.00%
14.00.00 JUNTAS DE DILATACION 8,756.28 0.00 0.00 0.00 8,756.28
14.01.00 JUNTAS ASFALTICAS 8,756.28 0.00 0.00 0.00 8,756.28
14.01.01 RELLENO DE JUNTAS CON ASFALTO ML 3,367.80 2.60 8,756.28 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 3,367.80 8,756.28 100.00%
15.00.00 SEÑALIZACION 19,345.30 0.00 0.00 0.00 19,345.30
15.01.00 SEÑALIZACION HORIZONTAL 19,345.30 0.00 0.00 0.00 19,345.30
15.01.01 PINTURA LINEAL EN SARDINEL ML 1,879.26 4.46 8,381.50 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,879.26 8,381.50 100.00%
15.01.02 PINTURA LINELA DISCONTINUA EJE VIA ML 1,000.00 6.16 6,160.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1,000.00 6,160.00 100.00%
15.01.03 PINTURA ZONAL (CRUCE PEATONAL) M2 20.00 10.11 202.20 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 202.20 100.00%
15.01.04 SEÑALIZACION REGLAMENTARIAS UND 32.00 18.80 601.60 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 601.60 100.00%
15.01.05 SEÑALES DE TRANSITO UND 20.00 200.00 4,000.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,000.00 100.00%
16.00.00 VARIOS 1,296.00 0.00 0.00 0.00 1,296.00
16.01.00 LIMPIEZA FINAL DE OBRA M2 7,200.00 0.18 1,296.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 7,200.00 1,296.00 100.00%
17.00.00 PLACA RECORDATORIA 802.12 0.00 0.00 0.00 802.12
17.01.00 PLACA RECORDATORIA UND 1.00 802.12 802.12 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 802.12 100.00%
1,574,019.93 132,758.38 200,867.56 333,625.94 1,240,394.06
GASTOS GENERALES 15% 236,102.99 19,913.76 30,130.13 50,043.89 186,059.11
SUB TOTAL 1,810,122.92 152,672.14 230,997.70 383,669.83 1,426,453.16
EXPEDIENTE TECNICO 22,000.00 1,855.56 2,807.52 4,663.07 17,336.93
SUPERVISION 60,000.00 5,060.61 7,656.86 12,717.47 47,282.53
COSTO DE LA OBRA 1,892,122.92 8.43% 159,588.31 12.76% 241,462.07 21.20% 401,050.38 78.80% 1,491,072.62
1,892,122.92
0.00
1,892,122.92
COSTO DIRECTO TOTAL

TERCERA VALORIZACION
PROYECTO
CORRESPONDIENTE AL MES DE : SETIEMBRE - 2013RESIDENTE DE OBRA : ING. RAUL CURASMA RAMOS FECHA DE PRESENTACION : 01/09/2013SUPERVISOR DE OBRA : ING. ALEX ANTONIO CARHUAMACA CANTO PERIODO : 01/09/2013 AL 30/09/2013DISTRITO : CHUPURO MONTO DEL PRESUPUESTO S/. 1,892,122.92PROVINCIA : HUANCAYO Avance Anterior 21.20%
DEPARTAMENTO : JUNIN Avance Actual 12.67% FECHA DE INICIO DE OBRA : 02/07/2013Avance Acumulado 33.86% PLAZO DE EJECUCION : 150 DiasSALDO 66.14% FECHA DE TERMINO PREVISTO : 02 DICIEMBRE DEL 2013
PARTIDA DESCRIPCIONPRESUPUESTO REFERENCIAL AVANCE
SALDO %
UND METRADOP.Unitario Presupuesto ANTERIOR ACTUAL ACUMULADO
S/. S/. METRADO VALORIZADO METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO
DESAGUE PLUVIAL01.00.00 TRABAJOS PRELIMINARES 1,219.98 1,219.98 0.00 1,219.98 0.00
01.01.00 TRAZO Y REPLANTEO ML 975.98 1.25 1,219.98 975.98 1,219.98 0.00 0.00 0.00% 975.98 1,219.98 100.00% 0.00 0.00 0.00%
02.00.00 MOVIMIENTO DE TIERRAS 46,612.23 41,286.26 4,212.50 45,498.76 1,113.53
02.01.00 EXCAVACIONES 46,612.23 41,286.26 4,212.50 45,498.76 1,113.53
02.01.01 EXCAVACION DE ZANJA CON MAQUINARIA DE TUBERIA PARA CONEXIÓN M3 838.00 11.00 9,218.00 756.89 8,325.79 81.11 892.21 9.68% 838.00 9,218.00 100.00% 0.00 0.00 0.00%
02.01.02 EXCAVACION ZANJA MANUAL SUMIDERO A MATRIZ DE DES.PLUVIAL DE TUB. ARA SUMIDERO A RED M3 137.98 25.58 3,529.53 137.98 3,529.53 0 0.00 0.00% 137.98 3,529.53 100.00% 0.00 0.00 0.00%
02.01.03 EXCAVACIONES PARA BUZONES M3 43.73 25.58 1,118.70 24.68 631.31 7.95 203.36 18.18% 32.63 834.68 74.61% 11.10 284.02 25.39%
02.01.04 EXCAVACION PARA SUMIDERO SUMIDERO TIPICO M3 41.92 25.58 1,072.25 41.92 1,072.31 0 0.00 0.00% 41.92 1,072.31 100.01% 0.00 0.00 0.00%
02.01.05 REFINE Y NIVELADO DE ZANJA P/TUBERIA DE TRAZO Y REPLANTEO ML 838.00 4.70 3,938.60 724.12 3,403.36 0 0.00 0.00% 724.12 3,403.36 86.41% 113.88 535.24 13.59%
02.01.06 PREPARACION CAMA DE APOYO ML 815.50 6.15 5,015.33 638.46 3,926.53 129.19 794.52 15.84% 767.65 4,721.05 94.13% 47.85 294.28 5.87%
02.01.07 RELLENO Y COMPACTADO DE ZANJA ML 815.50 27.86 22,719.83 732.14 20,397.42 83.36 2,322.41 10.22% 815.50 22,719.83 100.00% 0.00 0.00 0.00%
| OBRAS DE CONCRETO 30,355.71 3,795.11 14,932.77 18,727.88 11,627.83
03.01.00 BUZONES 30,355.71 3,795.11 14,932.77 18,727.88 11,627.83
03.01.01. ENCOFRADO Y DESENCOFRADO H=1,65 M2 93.06 16.17 1,504.78 30.85 498.84 34.996 565.89 37.61% 65.85 1,064.73 70.76% 27.21 440.05 29.24%
03.01.02 SOLADO DE CONCRETO fc=140kg/cm2 M3 3.98 212.73 847.20 1.19 253.15 1.19 253.15 29.88% 2.38 506.30 59.76% 1.60 340.90 40.24%
03.01.03 CONCRETO Fc=175 kg/cm2 en BUZON M3 17.52 262.31 4,596.46 8.48 2,224.39 2.1 550.85 11.98% 10.58 2,775.24 60.38% 6.94 1,821.22 39.62%
03.01.04 CONCRETO Fc=2175 kg/cm2 en teho h=0,20m M3 5.31 265.16 1,408.00 2.01 532.97 2.33 617.82 43.88% 4.34 1,150.79 81.73% 0.97 257.21 18.27%
03.01.05 ACERO DE REFUERZO Fy=4200 en buzones ML 30.00 5.55 166.50 9.00 49.95 12 66.60 40.00% 21.00 116.55 70.00% 9.00 49.95 30.00%
03.01.06 TARRAJEO INTERIOR BUZON M2 106.20 7.98 847.48 29.55 235.81 36 287.28 33.90% 65.55 523.09 61.72% 40.65 324.39 38.28%
03.01.07 MARCO Y TAPA DE FºFº EN BUZON UND 15.00 1,399.02 20,985.30 0.00 0.00 9 12,591.18 60.00% 9.00 12,591.18 60.00% 6.00 8,394.12 40.00%
04.00.00 SUMIDEROS 8,278.75 1,987.90 2,192.56 4,180.46 4,098.29
04.01.00 SUMIDEROS 8,278.75 1,987.90 2,192.56 4,180.46 4,098.29
04.01.01 ENCOFRADOY DESENCOFRADO DE SUMIDEROS M2 109.35 24.54 2,683.45 24.30 596.32 31.23 766.38 28.56% 55.53 1,362.71 50.78% 53.82 1,320.74 49.22%
04.01.02 CONCRETO Fc=175 kg/cm2 en sumideros M3 17.81 248.24 4,420.29 4.20 1,042.61 4.72 1,171.69 26.51% 8.92 2,214.30 50.09% 8.89 2,205.98 49.91%
04.01.03 ACERO REFUERZOfy=4200 EN SUMIDEROS EN MUROS KG 54.00 5.60 302.40 11.23 62.89 0.94 5.26 1.74% 12.17 68.15 22.54% 41.83 234.25 77.46%
04.01.04 TARRAJEO INTERIOR DE SUMIDERO M2 109.35 7.98 872.61 35.85 286.08 31.23 249.22 28.56% 67.08 535.30 61.34% 42.27 337.31 38.66%
05.00.00 SUMINISTRO E INSTALACIONES 59,794.41 51,257.41 5,754.68 57,012.08 2,782.33
05.01.00 RED DE TUBERIAS 57,957.06 50,849.11 5,022.46 55,871.57 2,085.50
05.01.01 TUBERIA MATRIZ PVC DE 8" ML 328.00 56.85 18,646.80 265.39 15,087.42 40.63 2,309.82 12.39% 306.02 17,397.24 93.30% 21.98 1,249.56 6.70%
05.01.02 TUBERIA MATRIZ PVC DE 10" ML 510.00 56.85 28,993.50 480.00 27,288.00 20.07 1,140.98 3.94% 500.07 28,428.98 98.05% 9.93 564.52 1.95%
05.01.03 TUBERIA CONEXIÓN SUMIDERO A MATRIZ UPVC 6" ML 137.98 74.77 10,316.76 113.33 8,473.68 21.02 1,571.67 15.23% 134.35 10,045.35 97.37% 3.63 271.42 2.63%
05.02.00 INSTALACIONES METALICAS 1,837.35 408.30 732.22 1,140.52 696.8305.02.01 VENTANA PARA SUMIDERO (0,70x0,25m) fierrosф 1/2 "ventana 70x30 UND 27.00 68.05 1,837.35 6.00 408.30 10.76 732.22 39.85% 16.76 1,140.52 62.07% 10.24 696.83 37.93%
"MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"

06.00.00 VARIOS 6,892.28 0.00 4,051.28 4,051.28 2,841.01
06.01.00 TAJEA EN PROG 0+520 4,051.28 0.00 4,051.28 4,051.28 0.00
06.01.01 TUBERIA UPVC 10" PROG 0+520 ML 15.00 248.24 3,723.60 0.00 0.00 15 3,723.60 100.00% 15.00 3,723.60 100.00% 0.00 0.00 0.00%
06.01.02 CONCRETO Fc=175 kg/cm2 en caja rompe presion M3 1.22 248.24 302.85 0.00 0.00 1.22 302.85 100.00% 1.22 302.85 100.00% 0.00 0.00 0.00%
06.01.03 CONCRETO Fc=175 kg/cm2 en tapa de caja M3 0.10 248.24 24.82 0.00 0.00 0.1 24.82 100.00% 0.10 24.82 100.00% 0.00 0.00 0.00%
06.02.00 TAJEA CONCRETO PROG 0+930 2,841.01 0.00 0.00 0.00 2,841.01
06.02.01 EXCAVACIONES MANUALES M3 5.40 25.58 138.13 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 5.40 138.13 100.00%
06.02.02 ENCOFRADO Y DESENCOFRADO M2 36.00 24.54 883.44 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 36.00 883.44 100.00%
06.02.03 SOLADO CONCRETO fc=140KG/CM2 M3 0.90 220.00 198.00 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 0.90 198.00 100.00%
06.02.04 CONCRETO Fc=175 kg/cm2 en ponton m3 2.70 248.24 670.25 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 2.70 670.25 100.00%
06.02.05 ACERO FY=4200 KG/CM2 KG 169.86 5.60 951.19 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 169.86 951.19 100.00%
PAVIMENTO RIGIDO07.00.00 OBRAS PROVISIONALES 3,231.42 2,009.82 321.60 2,331.42 900.00
07.01.00 ALMACEN Y CASETA DE GUARDIANIA dia 150.00 10.00 1,500.00 60.00 600.00 0 0.00 0.00% 60.00 600.00 40.00% 90.00 900.00 60.00%
07.02.00 MOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.00 480.00 480.00 0.33 158.40 0.67 321.60 67.00% 1.00 480.00 100.00% 0.00 0.00 0.00%
07.03.00 CARTE DE IDENTIFICACION DE OBRA und 1.00 1,251.42 1,251.42 1.00 1,251.42 0 0.00 0.00% 1.00 1,251.42 100.00% 0.00 0.00 0.00%
08.00.00 TRABAJOS PRELIMNARES 17,131.39 17,131.39 0.00 17,131.39 0.00
08.01.00 TRAZO DE NIVELES Y REPLANTEO (GENERAL) m2 7,344.00 1.06 7,784.64 7344.00 7,784.64 0 0.00 0.00% 7,344.00 7,784.64 100.00% 0.00 0.00 0.00%
08.02.00 DEMOLICION DE PAVIMENTO EXISTENTE m2 518.40 18.03 9,346.75 518.40 9,346.75 0 0.00 0.00% 518.40 9,346.75 100.00% 0.00 0.00 0.00%
09.00.00 MOVIMIENTO DE TIERRAS 10,516.20 9,738.80 311.66 10,050.45 465.01
09.01.00 CORTE DE TERRENO A NIVEL DE SUB RASANTE m3 2,570.40 3.69 9,484.78 2485.74 9,172.38 84.46 311.66 3.29% 2,570.20 9,484.04 99.99% 0.20 0.00 0.00%
09.02.00 EXCAVACION MANUAL PARA BADEN M3 23.72 9.37 222.26 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 23.72 222.26 100.00%
09.03.00 EXCAVACION MANUAL PARA SARDINEL M3 86.36 9.37 809.17 60.45 566.42 0 0.00 0.00% 60.45 566.42 70.00% 25.91 242.76 30.00%
10.00.00 ELIMINACION DE MATERIAL EXEDENTE 82,344.27 37,911.23 5,049.90 42,961.13 39,383.15
10.01.00 ACARREO INTERNO DE MATERIAL m3 3,216.57 15.30 49,213.57 903.19 13,818.81 15 229.50 0.47% 918.19 14,048.31 28.55% 2,298.38 35,165.26 71.45%
10.02.00 TRANSPORTE DE CARGIO(ELIMINACION) M3 3,216.57 10.30 33,130.70 2339.07 24,092.42 468 4,820.40 14.55% 2,807.07 28,912.82 87.27% 409.50 4,217.88 12.73%
11.00.00 PAVIMENTO RIGIDO 1,068,791.01 61,212.91 117,502.36 178,715.27 890,075.74
11.01.00 MEJORAMIENTO DE LA SUB RASANTE 248,404.79 28,665.50 23,980.09 52,645.59 195,759.20
11.01.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB RASANTE M3 1,321.92 79.30 104,828.26 132.19 10,482.67 149.23 11,833.94 11.29% 281.42 22,316.61 21.29% 1,040.50 82,511.65 78.71%
11.01.02 SELECCIÓN DE MATERIAL P7MEJ.SUB RASANTE(ZARANDEADO) M3 1,101.60 51.01 56,192.62 110.34 5,628.44 97.23 4,959.70 8.83% 207.57 10,588.15 18.84% 894.03 45,604.47 81.16%
11.01.03 CARGUIO P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 27.55 30,349.08 110.16 3,034.91 141 3,884.55 12.80% 251.16 6,919.46 22.80% 850.44 23,429.62 77.20%
11.01.04 TRANSORTE P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 15.30 16,854.48 110.16 1,685.45 0 0.00 0.00% 110.16 1,685.45 10.00% 991.44 15,169.03 90.00%
11.01.05 EXTR. RIEGO Y COMPACTACION MEJORAM. SUB RASANTE e= 0.15 MTS. M2 7,581.20 5.30 40,180.36 1478.12 7,834.04 623 3,301.90 8.22% 2,101.12 11,135.94 27.71% 5,480.08 29,044.42 72.29%
11.02.00 SUB BASE GRANULAR 820,386.22 32,547.41 93,522.27 126,069.67 694,316.54
11.02.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB BASE M3 1,812.21 79.30 143,708.25 181.22 14,370.75 141 11,181.30 7.78% 322.22 25,552.05 17.78% 1,489.99 118,156.21 82.22%
11.02.02 SELECCIÓN DE MATERIAL P7MEJ.SUB BASE(ZARANDEADO) M3 1,812.21 51.01 92,440.83 181.22 9,244.03 282.23 14,396.55 15.57% 463.45 23,640.58 25.57% 1,348.76 68,800.25 74.43%
11.02.03 CARGUIO P/MEJ. DE SUB BASE DE LA SELLECCION DEL MATERIAL M3 1,812.21 27.55 49,926.39 181.22 4,992.61 0 0.00 0.00% 181.22 4,992.61 10.00% 1,630.99 44,933.77 90.00%
11.02.04 EXTENDIDO Y RIEGO COMPACTADO M2 7,344.00 5.30 38,923.20 743.40 3,940.02 0 0.00 0.00% 743.40 3,940.02 10.12% 6,600.60 34,983.18 89.88%
11.02.05 ENCOFRADO Y DESENCOFRADO DE LOSA M2 1,387.20 28.78 39,923.62 0.00 0.00 189.22 5,445.75 13.64% 189.22 5,445.75 13.64% 1,197.98 34,477.86 86.36%
11.02.06 CONCRETO fc=210 kg/cm2 M3 1,550.96 281.26 436,223.01 0.00 0.00 212.68 59,818.38 13.71% 212.68 59,818.38 13.71% 1,338.28 376,404.63 86.29%
11.02.07 ACERO fy=4200kg/cm2 kg 3,492.00 5.51 19,240.92 0.00 0.00 486.44 2,680.28 13.93% 486.44 2,680.28 13.93% 3,005.56 16,560.64 86.07%
12.00.00 BADEN INTERSECCION DE VIAS Y SARDINELES 144,348.53 98,970.42 0.00 98,970.42 45,378.10
12.01.00 BADEN INTERSECCION DE VIAS 6,785.82 0.00 0.00 0.00 6,785.82
12.01.01 ENCOFRADO Y DESENCOFRADO DE BADEN M2 23.72 21.24 503.81 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 23.72 503.81 100.00%
12.01.02 CONCRETO fc=210 kg/cm2 en BADEN M3 23.72 264.84 6,282.00 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 23.72 6,282.00 100.00%
12.02.00 SARDINEL EXPUESTO 137,562.71 98,970.42 0.00 98,970.42 38,592.29
12.02.01 ENCOFRADO DESENCOFRADO SARDINEL EXPUESTO M2 1,968.00 51.02 100,407.36 1421.87 72,543.81 0 0.00 0.00% 1,421.87 72,543.81 72.25% 546.13 27,863.55 27.75%
12.02.02 CONCRETO fc=175kg/cm2 en sardinel M3 147.60 251.73 37,155.35 104.98 26,426.62 0 0.00 0.00% 104.98 26,426.62 71.12% 42.62 10,728.73 28.88%
13.00.00 OBRAS DE CONCRETO ARMADO 64,304.05 7,104.72 45,049.33 52,154.04 12,150.00
13.01.00 MURO DE CONTENCION 64,304.05 7,104.72 45,049.33 52,154.04 12,150.00

13.01.01 EXCAVACION MANUAL M3 318.00 26.39 8,392.02 269.22 7,104.72 48.78 1,287.30 15.34% 318.00 8,392.02 100.00% 0.00 0.00 0.00%
13.01.02 RELLENO CON MATERIAL SELECCIONADO M3 156.00 36.05 5,623.80 0.00 0.00 156 5,623.80 100.00% 156.00 5,623.80 100.00% 0.00 0.00 0.00%
13.01.03 CONCRETO fc=210 kg/cm2 en Muros M3 81.60 265.69 21,680.30 0.00 0.00 35.87 9,530.30 43.96% 35.87 9,530.30 43.96% 45.73 12,150.00 56.04%
13.01.04 ENCOFRADO Y DESENCOFRADO EN MUROS M2 561.00 28.41 15,938.01 0.00 0.00 561 15,938.01 100.00% 561.00 15,938.01 100.00% 0.00 0.00 0.00%
13.01.05 ACERO DE REFUEZO FY=4200 kg/cm2 kg 2,450.66 5.17 12,669.91 0.00 0.00 2450.66 12,669.91 100.00% 2,450.66 12,669.91 100.00% 0.00 0.00 0.00%
14.00.00 JUNTAS DE DILATACION 8,756.28 0.00 0.00 0.00 8,756.28
14.01.00 JUNTAS ASFALTICAS 8,756.28 0.00 0.00 0.00 8,756.28
14.01.01 RELLENO DE JUNTAS CON ASFALTO ML 3,367.80 2.60 8,756.28 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 3,367.80 8,756.28 100.00%
15.00.00 SEÑALIZACION 19,345.30 0.00 0.00 0.00 19,345.30
15.01.00 SEÑALIZACION HORIZONTAL 19,345.30 0.00 0.00 0.00 19,345.30
15.01.01 PINTURA LINEAL EN SARDINEL ML 1,879.26 4.46 8,381.50 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 1,879.26 8,381.50 100.00%
15.01.02 PINTURA LINELA DISCONTINUA EJE VIA ML 1,000.00 6.16 6,160.00 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 1,000.00 6,160.00 100.00%
15.01.03 PINTURA ZONAL (CRUCE PEATONAL) M2 20.00 10.11 202.20 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 20.00 202.20 100.00%
15.01.04 SEÑALIZACION REGLAMENTARIAS UND 32.00 18.80 601.60 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 32.00 601.60 100.00%
15.01.05 SEÑALES DE TRANSITO UND 20.00 200.00 4,000.00 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 20.00 4,000.00 100.00%
16.00.00 VARIOS 1,296.00 0.00 0.00 0.00 1,296.00
16.01.00 LIMPIEZA FINAL DE OBRA M2 7,200.00 0.18 1,296.00 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 7,200.00 1,296.00 100.00%
17.00.00 PLACA RECORDATORIA 802.12 0.00 0.00 0.00 802.12
17.01.00 PLACA RECORDATORIA UND 1.00 802.12 802.12 0.00 0.00 0 0.00 0.00% 0.00 0.00 0.00% 1.00 802.12 100.00%
1,574,019.93 333,625.94 199,378.62 533,004.56 1,041,014.70
GASTOS GENERALES 15% 236,102.99 50,043.89 29,906.79 79,950.68 156,152.20
SUB TOTAL 1,810,122.92 383,669.83 229,285.41 612,955.24 1,197,166.90
EXPEDIENTE TECNICO 22,000.00 4,663.07 2,786.71 7,449.78 14,550.21
SUPERVISION 60,000.00 12,717.47 7,600.11 20,317.58 39,682.40
COSTO DE LA OBRA 1,892,122.92 21.20% 401,050.38 12.67% 239,672.22 33.86% 640,722.60 66.14% 1,251,399.51
1,892,122.92
0.00
1,892,122.92
COSTO DIRECTO TOTAL

234

48.78
156
35.87
654.6
2750.66

CUARTA VALORIZACION
PROYECTO
CORRESPONDIENTE AL MES DE : OCTUBRE - 2013RESIDENTE DE OBRA : ING. RAUL CURASMA RAMOS FECHA DE PRESENTACION : 01/11/2013SUPERVISOR DE OBRA : ING. ALEX ANTONIO CARHUAMACA CANTO PERIODO : 01/10/2013 AL 31/10/2013DISTRITO : CHUPURO MONTO DEL PRESUPUESTO S/. 0.00PROVINCIA : HUANCAYO Avance Anterior 70.65%
DEPARTAMENTO : JUNIN Avance Actual 15.03% FECHA DE INICIO DE OBRA : 02/07/2013Avance Acumulado 85.68% PLAZO DE EJECUCION : 150 DiasSALDO 14.33% FECHA DE TERMINO PREVISTO : 02 DICIEMBRE DEL 2013
PARTIDA DESCRIPCIONPRESUPUESTO REFERENCIAL AVANCE
SALDO %
UND METRADOP.Unitario Presupuesto ANTERIOR ACTUAL ACUMULADO
S/. S/. METRADO VALORIZADO METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO
DESAGUE PLUVIAL01.00.00 TRABAJOS PRELIMINARES 1,219.98 1,219.98 0.00 1,219.98 0.00
01.01.00 TRAZO Y REPLANTEO ML 975.98 1.25 1,219.98 975.98 1,219.98 0.00 0.00% 975.98 1,219.98 100.00% 0.00 0.00 0.00%
02.00.00 MOVIMIENTO DE TIERRAS 46,612.23 46,012.00 661.60 46,673.60 0.08
02.01.00 EXCAVACIONES 46,612.23 46,012.00 661.60 46,673.60 0.08
02.01.01 EXCAVACION DE ZANJA CON MAQUINARIA DE TUBERIA PARA CONEXIÓN M3 838.00 11.00 9,218.00 838.00 9,218.00 0.00 0.00 0.00% 838.00 9,218.00 100.00% 0.00 0.00 0.00%
02.01.02 EXCAVACION ZANJA MANUAL SUMIDERO A MATRIZ DE DES.PLUVIAL DE TUB. ARA SUMIDERO A RED M3 137.98 25.58 3,529.53 137.98 3,529.53 0.00 0.00 0.00% 137.98 3,529.53 100.00% 0.00 0.00 0.00%
02.01.03 EXCAVACIONES PARA BUZONES M3 43.73 25.58 1,118.70 38.79 992.25 4.94 126.37 11.30% 43.73 1,118.61 100.00% 0.00 0.08 0.00%
02.01.04 EXCAVACION PARA SUMIDERO SUMIDERO TIPICO M3 41.92 25.58 1,072.25 44.32 1,133.71 0.00 0.00 0.00% 44.32 1,133.71 105.73% -2.40 0.00 0.00%
02.01.05 REFINE Y NIVELADO DE ZANJA P/TUBERIA DE TRAZO Y REPLANTEO ML 838.00 4.70 3,938.60 724.12 3,403.36 113.88 535.24 13.59% 838.00 3,938.60 100.00% 0.00 0.00 0.00%
02.01.06 PREPARACION CAMA DE APOYO ML 815.50 6.15 5,015.33 815.50 5,015.33 0.00 0.00 0.00% 815.50 5,015.33 100.00% 0.00 0.00 0.00%
02.01.07 RELLENO Y COMPACTADO DE ZANJA ML 815.50 27.86 22,719.83 815.50 22,719.83 0.00 0.00 0.00% 815.50 22,719.83 100.00% 0.00 0.00 0.00%
| OBRAS DE CONCRETO 30,355.71 20,305.25 7,251.04 27,556.82 2,798.04
03.01.00 BUZONES 30,355.71 20,305.25 7,251.04 27,556.82 2,798.04
03.01.01. ENCOFRADO Y DESENCOFRADO H=1,65 M2 93.06 16.17 1,504.78 73.08 1,181.64 19.98 323.08 21.47% 93.06 1,504.72 100.00% 0.00 0.00 0.00%
03.01.02 SOLADO DE CONCRETO fc=140kg/cm2 M3 3.98 212.73 847.20 2.66 565.86 1.32 280.80 33.15% 3.98 847.20 100.00% 0.00 0.00 0.00%
03.01.03 CONCRETO Fc=175 kg/cm2 en BUZON M3 17.52 262.31 4,596.46 15.27 4,005.47 2.25 590.20 12.84% 17.52 4,595.67 100.00% 0.00 0.00 0.00%
03.01.04 CONCRETO Fc=2175 kg/cm2 en teho h=0,20m M3 5.31 265.16 1,408.00 4.34 1,150.79 0.97 257.21 18.27% 5.31 1,408.00 100.00% 0.00 0.00 0.00%
03.01.05 ACERO DE REFUERZO Fy=4200 en buzones ML 30.00 5.55 166.50 24.10 133.76 5.90 32.75 19.67% 30.00 166.50 100.00% 0.00 0.00 0.00%
03.01.06 TARRAJEO INTERIOR BUZON M2 106.20 7.98 847.48 84.78 676.54 21.42 170.93 20.17% 106.20 847.48 100.00% 0.00 0.00 0.00%
03.01.07 MARCO Y TAPA DE FºFº EN BUZON UND 15.00 1,399.02 20,985.30 9.00 12,591.18 4.00 5,596.08 26.67% 13.00 18,187.26 86.67% 2.00 2,798.04 13.33%
04.00.00 SUMIDEROS 8,278.75 5,410.91 0.00 5,410.91 2,867.83
04.01.00 SUMIDEROS 8,278.75 5,410.91 0.00 5,410.91 2,867.83
04.01.01 ENCOFRADOY DESENCOFRADO DE SUMIDEROS M2 109.35 24.54 2,683.45 69.76 1,711.91 0.00 0.00 0.00% 69.76 1,711.91 63.80% 39.59 971.54 36.20%
04.01.02 CONCRETO Fc=175 kg/cm2 en sumideros M3 17.81 248.24 4,420.29 11.37 2,822.49 0.00 0.00 0.00% 11.37 2,822.49 63.85% 6.44 1,597.80 36.15%
04.01.03 ACERO REFUERZOfy=4200 EN SUMIDEROS EN MUROS KG 54.00 5.60 302.40 32.46 181.78 0.00 0.00 0.00% 32.46 181.78 60.11% 21.54 120.62 39.89%
04.01.04 TARRAJEO INTERIOR DE SUMIDERO M2 109.35 7.98 872.61 87.06 694.74 0.00 0.00 0.00% 87.06 694.74 79.62% 22.29 177.87 20.38%
05.00.00 SUMINISTRO E INSTALACIONES 59,794.41 58,533.06 564.52 59,097.58 696.83
05.01.00 RED DE TUBERIAS 57,957.06 57,392.54 564.52 57,957.06 0.00
05.01.01 TUBERIA MATRIZ PVC DE 8" ML 328.00 56.85 18,646.80 328.00 18,646.80 0.00 0.00 0.00% 328.00 18,646.80 100.00% 0.00 0.00 0.00%
05.01.02 TUBERIA MATRIZ PVC DE 10" ML 510.00 56.85 28,993.50 500.07 28,428.98 9.93 564.52 1.95% 510.00 28,993.50 100.00% 0.00 0.00 0.00%
05.01.03 TUBERIA CONEXIÓN SUMIDERO A MATRIZ UPVC 6" ML 137.98 74.77 10,316.76 137.98 10,316.76 0.00 0.00 0.00% 137.98 10,316.76 100.00% 0.00 0.00 0.00%
05.02.00 INSTALACIONES METALICAS 1,837.35 1,140.52 0.00 1,140.52 696.8305.02.01 VENTANA PARA SUMIDERO (0,70x0,25m) fierrosф 1/2 "ventana 70x30 UND 27.00 68.05 1,837.35 16.76 1,140.52 0.00 0.00 0.00% 16.76 1,140.52 62.07% 10.24 696.83 37.93%
"MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"

06.00.00 VARIOS 6,892.28 4,051.28 0.00 4,051.28 2,841.01
06.01.00 TAJEA EN PROG 0+520 4,051.28 4,051.28 0.00 4,051.28 0.00
06.01.01 TUBERIA UPVC 10" PROG 0+520 ML 15.00 248.24 3,723.60 15.00 3,723.60 0.00 0.00 0.00% 15.00 3,723.60 100.00% 0.00 0.00 0.00%
06.01.02 CONCRETO Fc=175 kg/cm2 en caja rompe presion M3 1.22 248.24 302.85 1.22 302.85 0.00 0.00 0.00% 1.22 302.85 100.00% 0.00 0.00 0.00%
06.01.03 CONCRETO Fc=175 kg/cm2 en tapa de caja M3 0.10 248.24 24.82 0.10 24.82 0.00 0.00 0.00% 0.10 24.82 100.00% 0.00 0.00 0.00%
06.02.00 TAJEA CONCRETO PROG 0+930 2,841.01 0.00 0.00 0.00 2,841.01
06.02.01 EXCAVACIONES MANUALES M3 5.40 25.58 138.13 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 5.40 138.13 100.00%
06.02.02 ENCOFRADO Y DESENCOFRADO M2 36.00 24.54 883.44 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 36.00 883.44 100.00%
06.02.03 SOLADO CONCRETO fc=140KG/CM2 M3 0.90 220.00 198.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.90 198.00 100.00%
06.02.04 CONCRETO Fc=175 kg/cm2 en ponton m3 2.70 248.24 670.25 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 2.70 670.25 100.00%
06.02.05 ACERO FY=4200 KG/CM2 KG 169.86 5.60 951.19 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 169.86 951.19 100.00%
PAVIMENTO RIGIDO07.00.00 OBRAS PROVISIONALES 3,231.42 2,631.42 300.00 2,931.42 300.00
07.01.00 ALMACEN Y CASETA DE GUARDIANIA dia 150.00 10.00 1,500.00 90.00 900.00 30.00 300.00 20.00% 120.00 1,200.00 80.00% 30.00 300.00 20.00%
07.02.00 MOVILIZACION DE EQUIPO Y MAQUINARIAS glb 1.00 480.00 480.00 1.00 480.00 0.00 0.00 0.00% 1.00 480.00 100.00% 0.00 0.00 0.00%
07.03.00 CARTE DE IDENTIFICACION DE OBRA und 1.00 1,251.42 1,251.42 1.00 1,251.42 0.00 0.00 0.00% 1.00 1,251.42 100.00% 0.00 0.00 0.00%
08.00.00 TRABAJOS PRELIMNARES 17,131.39 17,131.39 0.00 17,131.39 0.00
08.01.00 TRAZO DE NIVELES Y REPLANTEO (GENERAL) m2 7,344.00 1.06 7,784.64 7344.00 7,784.64 0.00 0.00 0.00% 7,344.00 7,784.64 100.00% 0.00 0.00 0.00%
08.02.00 DEMOLICION DE PAVIMENTO EXISTENTE m2 518.40 18.03 9,346.75 518.40 9,346.75 0.00 0.00 0.00% 518.40 9,346.75 100.00% 0.00 0.00 0.00%
09.00.00 MOVIMIENTO DE TIERRAS 10,516.20 10,115.76 156.95 10,272.71 242.76
09.01.00 CORTE DE TERRENO A NIVEL DE SUB RASANTE m3 2,570.40 3.69 9,484.78 2570.20 9,484.04 0.00 0.00 0.00% 2,570.20 9,484.04 100.00% 0.00 0.00 0.00%
09.02.00 EXCAVACION MANUAL PARA BADEN M3 23.72 9.37 222.26 6.97 65.31 16.75 156.95 70.62% 23.72 222.26 100.00% 0.00 0.00 0.00%
09.03.00 EXCAVACION MANUAL PARA SARDINEL M3 86.36 9.37 809.17 60.45 566.42 0.00 0.00 0.00% 60.45 566.42 70.00% 25.91 242.76 30.00%
10.00.00 ELIMINACION DE MATERIAL EXEDENTE 82,344.27 65,360.33 16,983.86 82,344.19 0.08
10.01.00 ACARREO INTERNO DE MATERIAL m3 3,216.57 15.30 49,213.57 2382.19 36,447.51 834.38 12,766.01 25.94% 3,216.57 49,213.52 100.00% 0.00 0.05 0.00%
10.02.00 TRANSPORTE DE CARGIO(ELIMINACION) M3 3,216.57 10.30 33,130.70 2807.07 28,912.82 409.50 4,217.85 12.73% 3,216.57 33,130.67 100.00% 0.00 0.03 0.00%
11.00.00 PAVIMENTO RIGIDO 1,068,791.01 722,701.46 180,280.51 902,981.97 165,809.04
11.01.00 MEJORAMIENTO DE LA SUB RASANTE 248,404.79 185,211.45 63,193.35 248,404.79 0.00
11.01.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB RASANTE M3 1,321.92 79.30 104,828.26 973.52 77,200.14 348.40 27,628.12 26.36% 1,321.92 104,828.26 100.00% 0.00 0.00 0.00%
11.01.02 SELECCIÓN DE MATERIAL P7MEJ.SUB RASANTE(ZARANDEADO) M3 1,101.60 51.01 56,192.62 786.89 40,139.26 314.71 16,053.36 28.57% 1,101.60 56,192.62 100.00% 0.00 0.00 0.00%
11.01.03 CARGUIO P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 27.55 30,349.08 830.48 22,879.72 271.12 7,469.36 24.61% 1,101.60 30,349.08 100.00% 0.00 0.00 0.00%
11.01.04 TRANSORTE P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL M3 1,101.60 15.30 16,854.48 694.49 10,625.70 407.11 6,228.78 36.96% 1,101.60 16,854.48 100.00% 0.00 0.00 0.00%
11.01.05 EXTR. RIEGO Y COMPACTACION MEJORAM. SUB RASANTE e= 0.15 MTS. M2 7,581.20 5.30 40,180.36 6484.27 34,366.63 1096.93 5,813.73 14.47% 7,581.20 40,180.36 100.00% 0.00 0.00 0.00%
11.02.00 SUB BASE GRANULAR 820,386.22 537,490.01 117,087.17 654,577.18 165,809.04
11.02.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB BASE M3 1,812.21 79.30 143,708.25 1201.50 95,278.95 610.71 48,429.30 33.70% 1,812.21 143,708.25 100.00% 0.00 0.00 0.00%
11.02.02 SELECCIÓN DE MATERIAL P7MEJ.SUB BASE(ZARANDEADO) M3 1,812.21 51.01 92,440.83 1342.73 68,492.66 234.74 11,974.09 12.95% 1,577.47 80,466.74 87.05% 234.74 11,974.09 12.95%
11.02.03 CARGUIO P/MEJ. DE SUB BASE DE LA SELLECCION DEL MATERIAL M3 1,812.21 27.55 49,926.39 1060.50 29,216.78 234.74 6,467.09 12.95% 1,295.24 35,683.86 71.47% 516.97 14,242.52 28.53%
11.02.04 EXTENDIDO Y RIEGO COMPACTADO M2 7,344.00 5.30 38,923.20 4517.41 23,942.27 1413.95 7,493.94 19.25% 5,931.36 31,436.21 80.76% 1,412.64 7,486.99 19.24%
11.02.05 ENCOFRADO Y DESENCOFRADO DE LOSA M2 1,387.20 28.78 39,923.62 884.53 25,456.77 251.24 7,230.69 18.11% 1,135.77 32,687.46 81.87% 251.43 7,236.16 18.13%
11.02.06 CONCRETO fc=210 kg/cm2 M3 1,550.96 281.26 436,223.01 1004.75 282,595.99 114.21 32,122.70 7.36% 1,118.96 314,718.69 72.15% 432.00 121,504.32 27.85%
11.02.07 ACERO fy=4200kg/cm2 kg 3,492.00 5.51 19,240.92 2269.80 12,506.60 611.50 3,369.37 17.51% 2,881.30 15,875.96 82.51% 610.70 3,364.96 17.49%
12.00.00 BADEN INTERSECCION DE VIAS Y SARDINELES 144,348.53 100,964.40 16,287.70 117,252.10 27,096.43
12.01.00 BADEN INTERSECCION DE VIAS 6,785.82 1,993.98 1,993.98 3,987.96 2,797.86
12.01.01 ENCOFRADO Y DESENCOFRADO DE BADEN M2 23.72 21.24 503.81 6.97 148.04 6.97 148.04 29.38% 13.94 296.09 58.77% 9.78 207.73 41.23%
12.01.02 CONCRETO fc=210 kg/cm2 en BADEN M3 23.72 264.84 6,282.00 6.97 1,845.93 6.97 1,845.93 29.38% 13.94 3,691.87 58.77% 9.78 2,590.14 41.23%
12.02.00 SARDINEL EXPUESTO 137,562.71 98,970.42 14,293.72 113,264.14 24,298.57
12.02.01 ENCOFRADO DESENCOFRADO SARDINEL EXPUESTO M2 1,968.00 51.02 100,407.36 1421.87 72,543.81 180.00 9,183.60 9.15% 1,601.87 81,727.41 81.40% 366.13 18,679.95 18.60%
12.02.02 CONCRETO fc=175kg/cm2 en sardinel M3 147.60 251.73 37,155.35 104.98 26,426.62 20.30 5,110.12 13.75% 125.28 31,536.73 84.88% 22.32 5,618.61 15.12%
13.00.00 OBRAS DE CONCRETO ARMADO 64,304.05 52,154.04 12,150.00 64,304.05 0.00
13.01.00 MURO DE CONTENCION 64,304.05 52,154.04 12,150.00 64,304.05 0.00

13.01.01 EXCAVACION MANUAL M3 318.00 26.39 8,392.02 318.00 8,392.02 0.00 0.00 0.00% 318.00 8,392.02 100.00% 0.00 0.00 0.00%
13.01.02 RELLENO CON MATERIAL SELECCIONADO M3 156.00 36.05 5,623.80 156.00 5,623.80 0.00 0.00 0.00% 156.00 5,623.80 100.00% 0.00 0.00 0.00%
13.01.03 CONCRETO fc=210 kg/cm2 en Muros M3 81.60 265.69 21,680.30 35.87 9,530.30 45.73 12,150.00 56.04% 81.60 21,680.30 100.00% 0.00 0.00 0.00%
13.01.04 ENCOFRADO Y DESENCOFRADO EN MUROS M2 561.00 28.41 15,938.01 561.00 15,938.01 0.00 0.00 0.00% 561.00 15,938.01 100.00% 0.00 0.00 0.00%
13.01.05 ACERO DE REFUEZO FY=4200 kg/cm2 kg 2,450.66 5.17 12,669.91 2450.66 12,669.91 0.00 0.00 0.00% 2,450.66 12,669.91 100.00% 0.00 0.00 0.00%
14.00.00 JUNTAS DE DILATACION 8,756.28 2,189.07 1,947.40 4,136.47 4,619.81
14.01.00 JUNTAS ASFALTICAS 8,756.28 2,189.07 1,947.40 4,136.47 4,619.81
14.01.01 RELLENO DE JUNTAS CON ASFALTO ML 3,367.80 2.60 8,756.28 841.95 2,189.07 749.00 1,947.40 22.24% 1,590.95 4,136.47 47.24% 1,776.85 4,619.81 52.76%
15.00.00 SEÑALIZACION 19,345.30 3,016.00 0.00 3,016.00 16,329.30
15.01.00 SEÑALIZACION HORIZONTAL 19,345.30 3,016.00 0.00 3,016.00 16,329.30
15.01.01 PINTURA LINEAL EN SARDINEL ML 1,879.26 4.46 8,381.50 400.00 1,784.00 0.00 0.00 0.00% 400.00 1,784.00 21.28% 1,479.26 6,597.50 78.72%
15.01.02 PINTURA LINELA DISCONTINUA EJE VIA ML 1,000.00 6.16 6,160.00 200.00 1,232.00 0.00 0.00 0.00% 200.00 1,232.00 20.00% 800.00 4,928.00 80.00%
15.01.03 PINTURA ZONAL (CRUCE PEATONAL) M2 20.00 10.11 202.20 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 202.20 100.00%
15.01.04 SEÑALIZACION REGLAMENTARIAS UND 32.00 18.80 601.60 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 32.00 601.60 100.00%
15.01.05 SEÑALES DE TRANSITO UND 20.00 200.00 4,000.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 4,000.00 100.00%
16.00.00 VARIOS 1,296.00 219.60 0.00 219.60 1,076.40
16.01.00 LIMPIEZA FINAL DE OBRA M2 7,200.00 0.18 1,296.00 1220.00 219.60 0.00 0.00 0.00% 1,220.00 219.60 16.94% 5,980.00 1,076.40 83.06%
17.00.00 PLACA RECORDATORIA 802.12 0.00 0.00 0.00 802.12
17.01.00 PLACA RECORDATORIA UND 1.00 802.12 802.12 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 802.12 100.00%
1,574,019.93 1,112,015.95 236,583.59 1,348,600.07 225,479.73
GASTOS GENERALES 15% 236,102.99 166,802.39 35,487.54 202,290.01 33,821.96
SUB TOTAL 1,810,122.92 1,278,818.35 272,071.13 1,550,890.09 259,301.69
EXPEDIENTE TECNICO 22,000.00 15,542.59 3,306.72 18,849.31 3,151.52
SUPERVISION 60,000.00 42,388.89 9,018.32 51,407.21 8,595.05
COSTO DE LA OBRA 1,892,122.92 70.65% 1,336,749.83 15.03% 284,396.16 85.68% 1,621,146.60 14.33% 271,048.26
COSTO DIRECTO TOTAL

PROYECTO "MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"
RESIDENTE DE OBRA : ING. RAUL CURASMA RAMOS
SUPERVISOR DE OBRA : ING. ALEX ANTONIO CARHUAMACA CANTO
DISTRITO : CHUPURO
PROVINCIA : HUANCAYO
DEPARTAMENTO : JUNIN
PARTIDA DESCRIPCION
DESAGUE PLUVIAL01.00.00 TRABAJOS PRELIMINARES
01.01.00 TRAZO Y REPLANTEO
02.00.00 MOVIMIENTO DE TIERRAS
02.01.00 EXCAVACIONES
02.01.01 EXCAVACION DE ZANJA CON MAQUINARIA DE TUBERIA PARA CONEXIÓN
02.01.02 EXCAVACION ZANJA MANUAL SUMIDERO A MATRIZ DE DES.PLUVIAL DE TUB. ARA SUMIDERO A RED MATRIZ
02.01.03 EXCAVACIONES PARA BUZONES
02.01.04 EXCAVACION PARA SUMIDERO SUMIDERO TIPICO
02.01.05 REFINE Y NIVELADO DE ZANJA P/TUBERIA DE TRAZO Y REPLANTEO
02.01.06 PREPARACION CAMA DE APOYO
02.01.07 RELLENO Y COMPACTADO DE ZANJA
| OBRAS DE CONCRETO
03.01.00 BUZONES
03.01.01. ENCOFRADO Y DESENCOFRADO H=1,65
03.01.02 SOLADO DE CONCRETO fc=140kg/cm2
03.01.03 CONCRETO Fc=175 kg/cm2 en BUZON
03.01.04 CONCRETO Fc=2175 kg/cm2 en teho h=0,20m
03.01.05 ACERO DE REFUERZO Fy=4200 en buzones
03.01.06 TARRAJEO INTERIOR BUZON
03.01.07 MARCO Y TAPA DE FºFº EN BUZON
04.00.00 SUMIDEROS
04.01.00 SUMIDEROS
04.01.01 ENCOFRADOY DESENCOFRADO DE SUMIDEROS
04.01.02 CONCRETO Fc=175 kg/cm2 en sumideros
04.01.03 ACERO REFUERZOfy=4200 EN SUMIDEROS EN MUROS
04.01.04 TARRAJEO INTERIOR DE SUMIDERO
05.00.00 SUMINISTRO E INSTALACIONES
05.01.00 RED DE TUBERIAS
05.01.01 TUBERIA MATRIZ PVC DE 8"

05.01.02 TUBERIA MATRIZ PVC DE 10"
05.01.03 TUBERIA CONEXIÓN SUMIDERO A MATRIZ UPVC 6"
05.02.00 INSTALACIONES METALICAS
05.02.01 VENTANA PARA SUMIDERO (0,70x0,25m) fierrosф 1/2 "ventana 70x30
06.00.00 VARIOS
06.01.00 TAJEA EN PROG 0+520
06.01.01 TUBERIA UPVC 10" PROG 0+520
06.01.02 CONCRETO Fc=175 kg/cm2 en caja rompe presion
06.01.03 CONCRETO Fc=175 kg/cm2 en tapa de caja
06.02.00 TAJEA CONCRETO PROG 0+930
06.02.01 EXCAVACIONES MANUALES
06.02.02 ENCOFRADO Y DESENCOFRADO
06.02.03 SOLADO CONCRETO fc=140KG/CM2
06.02.04 CONCRETO Fc=175 kg/cm2 en ponton
06.02.05 ACERO FY=4200 KG/CM2
PAVIMENTO RIGIDO07.00.00 OBRAS PROVISIONALES
07.01.00 ALMACEN Y CASETA DE GUARDIANIA
07.02.00 MOVILIZACION DE EQUIPO Y MAQUINARIAS
07.03.00 CARTE DE IDENTIFICACION DE OBRA
08.00.00 TRABAJOS PRELIMNARES
08.01.00 TRAZO DE NIVELES Y REPLANTEO (GENERAL)
08.02.00 DEMOLICION DE PAVIMENTO EXISTENTE
09.00.00 MOVIMIENTO DE TIERRAS
09.01.00 CORTE DE TERRENO A NIVEL DE SUB RASANTE
09.02.00 EXCAVACION MANUAL PARA BADEN
09.03.00 EXCAVACION MANUAL PARA SARDINEL
10.00.00 ELIMINACION DE MATERIAL EXEDENTE
10.01.00 ACARREO INTERNO DE MATERIAL
10.02.00 TRANSPORTE DE CARGIO(ELIMINACION)
11.00.00 PAVIMENTO RIGIDO
11.01.00 MEJORAMIENTO DE LA SUB RASANTE
11.01.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB RASANTE
11.01.02 SELECCIÓN DE MATERIAL P7MEJ.SUB RASANTE(ZARANDEADO)
11.01.03 CARGUIO P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL
11.01.04 TRANSORTE P/MEJ. DE SUB RASANTE DE LA SELLECCION DEL MATERIAL
11.01.05 EXTR. RIEGO Y COMPACTACION MEJORAM. SUB RASANTE e= 0.15 MTS.
11.02.00 SUB BASE GRANULAR
11.02.01 EXTRACCION DE MATERIAL P/MEJ. DE SUB BASE
11.02.02 SELECCIÓN DE MATERIAL P7MEJ.SUB BASE(ZARANDEADO)
11.02.03 CARGUIO P/MEJ. DE SUB BASE DE LA SELLECCION DEL MATERIAL
11.02.04 EXTENDIDO Y RIEGO COMPACTADO
11.02.05 ENCOFRADO Y DESENCOFRADO DE LOSA
11.02.06 CONCRETO fc=210 kg/cm2
11.02.07 ACERO fy=4200kg/cm2

12.00.00 BADEN INTERSECCION DE VIAS Y SARDINELES
12.01.00 BADEN INTERSECCION DE VIAS
12.01.01 ENCOFRADO Y DESENCOFRADO DE BADEN
12.01.02 CONCRETO fc=210 kg/cm2 en BADEN
12.02.00 SARDINEL EXPUESTO
12.02.01 ENCOFRADO DESENCOFRADO SARDINEL EXPUESTO
12.02.02 CONCRETO fc=175kg/cm2 en sardinel
13.00.00 OBRAS DE CONCRETO ARMADO
13.01.00 MURO DE CONTENCION
13.01.01 EXCAVACION MANUAL
13.01.02 RELLENO CON MATERIAL SELECCIONADO
13.01.03 CONCRETO fc=210 kg/cm2 en Muros
13.01.04 ENCOFRADO Y DESENCOFRADO EN MUROS
13.01.05 ACERO DE REFUEZO FY=4200 kg/cm2
14.00.00 JUNTAS DE DILATACION
14.01.00 JUNTAS ASFALTICAS
14.01.01 RELLENO DE JUNTAS CON ASFALTO
15.00.00 SEÑALIZACION
15.01.00 SEÑALIZACION HORIZONTAL
15.01.01 PINTURA LINEAL EN SARDINEL
15.01.02 PINTURA LINELA DISCONTINUA EJE VIA
15.01.03 PINTURA ZONAL (CRUCE PEATONAL)
15.01.04 SEÑALIZACION REGLAMENTARIAS
15.01.05 SEÑALES DE TRANSITO
16.00.00 VARIOS
16.01.00 LIMPIEZA FINAL DE OBRA
17.00.00 PLACA RECORDATORIA
17.01.00 PLACA RECORDATORIA
GASTOS GENERALES 15%
SUB TOTAL
EXPEDIENTE TECNICO
SUPERVISION
COSTO DE LA OBRA
COSTO DIRECTO TOTAL

"MEJORAMIENTO VIAL DEL JR. LA MERCED - AV LOS INCAS DEL DISTRITO DE CHUPURO, PROVINCIA DE HUANCAYO DEPARTAMENTO JUNIN"CORRESPONDIENTE AL MES DE FECHA DE PRESENTACIONPERIODOMONTO DEL PRESUPUESTO
Avance Anterior 70.65%
Avance Actual 0.53% FECHA DE INICIO DE OBRAAvance Acumulado 71.17% PLAZO DE EJECUCION
SALDO 28.83% FECHA DE TERMINO PREVISTO
PRESUPUESTO REFERENCIAL AVANCE
UND METRADOP.Unitario Presupuesto ANTERIOR ACTUAL
S/. S/. METRADO VALORIZADO METRADO
1,219.98 1,219.98
ML 975.98 1.25 1,219.98 975.98 1,219.98 0.00
46,612.23 46,012.00
46,612.23 46,012.00
M3 838.00 11.00 9,218.00 838.00 9,218.00 0.00
M3 137.98 25.58 3,529.53 137.98 3,529.53 0.00
M3 43.73 25.58 1,118.70 38.79 992.25 6.16
M3 41.92 25.58 1,072.25 44.32 1,133.71 0.00
ML 838.00 4.70 3,938.60 724.12 3,403.36 113.88
ML 815.50 6.15 5,015.33 815.50 5,015.33 0.00
ML 815.50 27.86 22,719.83 815.50 22,719.83 0.00
30,355.71 20,305.25
30,355.71 20,305.25
M2 93.06 16.17 1,504.78 73.08 1,181.64 19.98
M3 3.98 212.73 847.20 2.66 565.86 1.32
M3 17.52 262.31 4,596.46 15.27 4,005.47 2.25
M3 5.31 265.16 1,408.00 4.34 1,150.79 0.97
ML 30.00 5.55 166.50 24.10 133.76 5.90
M2 106.20 7.98 847.48 84.78 676.54 21.42
UND 15.00 1,399.02 20,985.30 9.00 12,591.18 3.00
8,278.75 5,410.91
8,278.75 5,410.91
M2 109.35 24.54 2,683.45 69.76 1,711.91 0.00
M3 17.81 248.24 4,420.29 11.37 2,822.49 2.45
KG 54.00 5.60 302.40 32.46 181.78 20.29
M2 109.35 7.98 872.61 87.06 694.74 19.98
59,794.41 58,533.06
57,957.06 57,392.54
ML 328.00 56.85 18,646.80 328.00 18,646.80 0.00

ML 510.00 56.85 28,993.50 500.07 28,428.98 9.93
ML 137.98 74.77 10,316.76 137.98 10,316.76 0.00
1,837.35 1,140.52
UND 27.00 68.05 1,837.35 16.76 1,140.52 0.00
6,892.28 4,051.28
4,051.28 4,051.28
ML 15.00 248.24 3,723.60 15.00 3,723.60 0.00
M3 1.22 248.24 302.85 1.22 302.85 0.00
M3 0.10 248.24 24.82 0.10 24.82 0.00
2,841.01 0.00
M3 5.40 25.58 138.13 0.00 0.00 0.00
M2 36.00 24.54 883.44 0.00 0.00 0.00
M3 0.90 220.00 198.00 0.00 0.00 0.00
m3 2.70 248.24 670.25 0.00 0.00 0.00
KG 169.86 5.60 951.19 0.00 0.00 0.00
3,231.42 2,631.42
dia 150.00 10.00 1,500.00 90.00 900.00 30.00
glb 1.00 480.00 480.00 1.00 480.00 0.00
und 1.00 1,251.42 1,251.42 1.00 1,251.42 0.00
17,131.39 17,131.39
m2 7,344.00 1.06 7,784.64 7344.00 7,784.64 0.00
m2 518.40 18.03 9,346.75 518.40 9,346.75 0.00
10,516.20 10,115.76
m3 2,570.40 3.69 9,484.78 2570.20 9,484.04 0.00
M3 23.72 9.37 222.26 6.97 65.31 0.00
M3 86.36 9.37 809.17 60.45 566.42 0.00
82,344.27 65,360.33
m3 3,216.57 15.30 49,213.57 2382.19 36,447.51 0.00
M3 3,216.57 10.30 33,130.70 2807.07 28,912.82 0.00
1,068,791.01 722,701.46
248,404.79 185,211.45
M3 1,321.92 79.30 104,828.26 973.52 77,200.14 0.00
M3 1,101.60 51.01 56,192.62 786.89 40,139.26 0.00
M3 1,101.60 27.55 30,349.08 830.48 22,879.72 0.00
M3 1,101.60 15.30 16,854.48 694.49 10,625.70 0.00
M2 7,581.20 5.30 40,180.36 6484.27 34,366.63 0.00
820,386.22 537,490.01
M3 1,812.21 79.30 143,708.25 1201.50 95,278.95 0.00
M3 1,812.21 51.01 92,440.83 1342.73 68,492.66 0.00
M3 1,812.21 27.55 49,926.39 1060.50 29,216.78 0.00
M2 7,344.00 5.30 38,923.20 4517.41 23,942.27 0.00
M2 1,387.20 28.78 39,923.62 884.53 25,456.77 0.00
M3 1,550.96 281.26 436,223.01 1004.75 282,595.99 0.00
kg 3,492.00 5.51 19,240.92 2269.80 12,506.60 0.00

144,348.53 100,964.40
6,785.82 1,993.98
M2 23.72 21.24 503.81 6.97 148.04 0.00
M3 23.72 264.84 6,282.00 6.97 1,845.93 0.00
137,562.71 98,970.42
M2 1,968.00 51.02 100,407.36 1421.87 72,543.81 0.00
M3 147.60 251.73 37,155.35 104.98 26,426.62 0.00
64,304.05 52,154.04
64,304.05 52,154.04
M3 318.00 26.39 8,392.02 318.00 8,392.02 0.00
M3 156.00 36.05 5,623.80 156.00 5,623.80 0.00
M3 81.60 265.69 21,680.30 35.87 9,530.30 0.00
M2 561.00 28.41 15,938.01 561.00 15,938.01 0.00
kg 2,450.66 5.17 12,669.91 2450.66 12,669.91 0.00
8,756.28 2,189.07
8,756.28 2,189.07
ML 3,367.80 2.60 8,756.28 841.95 2,189.07 0.00
19,345.30 3,016.00
19,345.30 3,016.00
ML 1,879.26 4.46 8,381.50 400.00 1,784.00 0.00
ML 1,000.00 6.16 6,160.00 200.00 1,232.00 0.00
M2 20.00 10.11 202.20 0.00 0.00 0.00
UND 32.00 18.80 601.60 0.00 0.00 0.00
UND 20.00 200.00 4,000.00 0.00 0.00 0.00
1,296.00 219.60
M2 7,200.00 0.18 1,296.00 1220.00 219.60 0.00
802.12 0.00
UND 1.00 802.12 802.12 0.00 0.00 0.00
1,574,019.93 1,112,015.95
GASTOS GENERALES 15% 236,102.99 166,802.39
SUB TOTAL 1,810,122.92 1,278,818.35
22,000.00 15,542.59
60,000.00 42,388.89
1,892,122.92 70.65% 1,336,749.83 0.53%

CORRESPONDIENTE AL MES DE : OCTUBRE - 2013FECHA DE PRESENTACION : 01/11/2013
: 01/10/2013 AL 31/10/2013MONTO DEL PRESUPUESTO S/. 0.00
FECHA DE INICIO DE OBRA : 02/07/2013PLAZO DE EJECUCION : 150 DiasFECHA DE TERMINO PREVISTO : 02 DICIEMBRE DEL 2013
AVANCESALDO
ACTUAL ACUMULADOVALORIZADO % METRADO VALORIZADO % METRADO
0.00 1,219.98
0.00 0.00% 975.98 1,219.98 100.00% 0.00
692.81 46,673.69
692.81 46,673.69
0.00 0.00% 838.00 9,218.00 100.00% 0.00
0.00 0.00% 137.98 3,529.53 100.00% 0.00
157.57 14.09% 44.95 1,118.70 100.00% -1.22
0.00 0.00% 44.32 1,133.71 105.73% 0.00
535.24 13.59% 838.00 3,938.60 100.00% 0.00
0.00 0.00% 815.50 5,015.33 100.00% 0.00
0.00 0.00% 815.50 22,719.83 100.00% 0.00
5,852.02 26,157.27
5,852.02 26,157.27
323.08 21.47% 93.06 1,504.72 100.00% 0.00
280.80 33.15% 3.98 846.67 100.00% 0.00
590.20 12.84% 17.52 4,595.67 99.98% 0.00
257.21 18.27% 5.31 1,408.00 100.00% 0.00
32.75 19.67% 30.00 166.50 100.00% 0.00
170.93 20.17% 106.20 847.48 100.00% 0.00
4,197.06 20.00% 12.00 16,788.24 80.00% 3.00
881.25 6,292.17
881.25 6,292.17
0.00 0.00% 69.76 1,711.91 63.80% 39.59
608.19 13.76% 13.82 3,430.68 77.61% 3.99
113.62 37.57% 52.75 295.40 97.69% 1.25
159.44 18.27% 107.04 854.18 97.89% 2.31
564.52 59,097.58
564.52 57,957.06
0.00 0.00% 328.00 18,646.80 100.00% 0.00

564.52 1.95% 510.00 28,993.50 100.00% 0.00
0.00 0.00% 137.98 10,316.76 100.00% 0.00
0.00 1,140.52
0.00 0.00% 16.76 1,140.52 62.07% 10.24
0.00 4,051.28
0.00 4,051.28
0.00 0.00% 15.00 3,723.60 100.00% 0.00
0.00 0.00% 1.22 302.85 100.00% 0.00
0.00 0.00% 0.10 24.82 100.00% 0.00
0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 5.40
0.00 0.00% 0.00 0.00 0.00% 36.00
0.00 0.00% 0.00 0.00 0.00% 0.90
0.00 0.00% 0.00 0.00 0.00% 2.70
0.00 0.00% 0.00 0.00 0.00% 169.86
300.00 2,931.42
300.00 20.00% 120.00 1,200.00 80.00% 30.00
0.00 0.00% 1.00 480.00 100.00% 0.00
0.00 0.00% 1.00 1,251.42 100.00% 0.00
0.00 17,131.39
0.00 0.00% 7,344.00 7,784.64 100.00% 0.00
0.00 0.00% 518.40 9,346.75 100.00% 0.00
0.00 10,115.76
0.00 0.00% 2,570.20 9,484.04 99.99% 0.20
0.00 0.00% 6.97 65.31 29.38% 16.75
0.00 0.00% 60.45 566.42 70.00% 25.91
0.00 65,360.33
0.00 0.00% 2,382.19 36,447.51 74.06% 834.38
0.00 0.00% 2,807.07 28,912.82 87.27% 409.50
0.00 722,701.46
0.00 185,211.45
0.00 0.00% 973.52 77,200.14 73.64% 348.40
0.00 0.00% 786.89 40,139.26 71.43% 314.71
0.00 0.00% 830.48 22,879.72 75.39% 271.12
0.00 0.00% 694.49 10,625.70 63.04% 407.11
0.00 0.00% 6,484.27 34,366.63 85.53% 1,096.93
0.00 537,490.01
0.00 0.00% 1,201.50 95,278.95 66.30% 610.71
0.00 0.00% 1,342.73 68,492.66 74.09% 469.48
0.00 0.00% 1,060.50 29,216.78 58.52% 751.71
0.00 0.00% 4,517.41 23,942.27 61.51% 2,826.59
0.00 0.00% 884.53 25,456.77 63.76% 502.67
0.00 0.00% 1,004.75 282,595.99 64.78% 546.21
0.00 0.00% 2,269.80 12,506.60 65.00% 1,222.20

0.00 100,964.40
0.00 1,993.98
0.00 0.00% 6.97 148.04 29.38% 16.75
0.00 0.00% 6.97 1,845.93 29.38% 16.75
0.00 98,970.42
0.00 0.00% 1,421.87 72,543.81 72.25% 546.13
0.00 0.00% 104.98 26,426.62 71.12% 42.62
0.00 52,154.04
0.00 52,154.04
0.00 0.00% 318.00 8,392.02 100.00% 0.00
0.00 0.00% 156.00 5,623.80 100.00% 0.00
0.00 0.00% 35.87 9,530.30 43.96% 45.73
0.00 0.00% 561.00 15,938.01 100.00% 0.00
0.00 0.00% 2,450.66 12,669.91 100.00% 0.00
0.00 2,189.07
0.00 2,189.07
0.00 0.00% 841.95 2,189.07 25.00% 2,525.85
0.00 3,016.00
0.00 3,016.00
0.00 0.00% 400.00 1,784.00 21.28% 1,479.26
0.00 0.00% 200.00 1,232.00 20.00% 800.00
0.00 0.00% 0.00 0.00 0.00% 20.00
0.00 0.00% 0.00 0.00 0.00% 32.00
0.00 0.00% 0.00 0.00 0.00% 20.00
0.00 219.60
0.00 0.00% 1,220.00 219.60 16.94% 5,980.00
0.00 0.00
0.00 0.00% 0.00 0.00 0.00% 1.00
8,290.60 1,120,275.43
1,243.59 168,041.31
9,534.19 1,288,316.75
115.88 15,658.47
316.03 42,704.92
9,966.10 71.17% 1,346,680.14 28.83%

SALDO %
VALORIZADO
0.00
0.00 0.00% 0
0.00
0.00
0.00 0.00% 0
0.00 0.00% 0
0.00 0.00% 0.11303185
0.00 0.00% 0
0.00 0.00% 0.13589499
0.00 0.00% 0
0.00 0.00% 0
4,197.06
4,197.06
0.00 0.00% 0.21474318
0.00 0.00% 0.33207784
0.00 0.00% 0.12857387
0.00 0.00% 0.1826742
0.00 0.00% 0.19666667
0.00 0.00% 0.20169492
4,197.06 20.00% 0.4
1,986.58
1,986.58
971.54 36.20% 0.36204847
989.61 22.39% 0.36146913
7.00 2.31% 0.39888889
18.43 2.11% 0.20384088
696.83
0.00
0.00 0.00% 0

0.00 0.00% 0.01947059
0.00 0.00% 0
696.83
696.83 37.93% 0.37925926
2,841.01
0.00
0.00 0.00% 0
0.00 0.00% 0
0.00 0.00% 0
2,841.01
138.13 100.00% 1
883.44 100.00% 1
198.00 100.00% 1
670.25 100.00% 1
951.19 100.00% 1
300.00
300.00 20.00% 0.4
0.00 0.00% 0
0.00 0.00% 0
0.00
0.00 0.00% 0
0.00 0.00% 0
399.70
0.00 0.00% 7.7809E-05
156.95 70.62% 0.70615514
242.76 30.00% 0.30000452
16,983.95
12,766.06 25.94% 0.25940129
4,217.88 12.73% 0.1273104
346,089.55
63,193.35
27,628.12 26.36% 0.26355604
16,053.36 28.57% 0.28568446
7,469.36 24.61% 0.24611474
6,228.78 36.96% 0.36956245
5,813.73 14.47% 0.14469081
282,896.20
48,429.30 33.70% 0.33699737
23,948.17 25.91% 0.2590649
20,709.61 41.48% 0.41480292
14,980.93 38.49% 0.38488426
14,466.84 36.24% 0.36236303
153,627.02 35.22% 0.35217543
6,734.32 35.00% 0.35

43,384.13
4,791.84
355.77 70.62% 0.70615514
4,436.07 70.62% 0.70615514
38,592.29
27,863.55 27.75% 0.27750508
10,728.73 28.88% 0.28875339
12,150.00
12,150.00
0.00 0.00% 0
0.00 0.00% 0
12,150.00 56.04% 0.56041667
0.00 0.00% 0
0.00 0.00% 0
6,567.21
6,567.21
6,567.21 75.00% 0.75
16,329.30
16,329.30
6,597.50 78.72% 0.78715026
4,928.00 80.00% 0.8
202.20 100.00% 1
601.60 100.00% 1
4,000.00 100.00% 1
1,076.40
1,076.40 83.06% 0.83055556
802.12
802.12 100.00% 1
453,803.84
68,070.58
521,874.41
6,342.79
17,298.53
545,515.74